Hi Jacopo,
what if some manufacturing unit have 10-15 routing task then it is not feasible 
to have that many production runs. Don't you think there is some better way out 
?

Thanks
Brijesh M.


Jacopo Cappellato <[EMAIL PROTECTED]> wrote: But there should be also another 
production run for the other part of  
the product/task.

Jacopo

On Jul 24, 2008, at 3:46 PM, brijesh m wrote:

> Hi Jacopo,
> I have tried by this way also but when creating the production run  
> for finished good it shows only the requirement of RAW_C and RAW_D  
> but it has to show requirement for RAW_A and RAW_B to be effective.  
> It shows that routing task A is needed but nothing else.
>
> Thanks
> Brijesh M.
>
> Jacopo Cappellato  wrote: Your BOM is  
> not setup correctly. You should have something like this:
>
> RAW_C
> |
> |________> RAW_A
> |
> |________> RAW_B
>
>
> FINISHED_GOOD
> |
> |________> RAW_C
> |
> |________> RAW_D
>
>
> The only one you have to define as WIP is RAW_C
>
> Jacopo
>
>
>
> On Jul 24, 2008, at 2:18 PM, brijesh m wrote:
>
>> Hi Jacopo,
>> I have created this example on :
>> https://demo.hotwaxmedia.com/manufacturing/control/main
>> here I have created
>>
>>  Ram materials as RAW_A, RAW_B, RAW_D and RAW_C as work in progress.
>>   I have created two routing tasks as TASK_A and TASK_B. Task_A
>> uses RAW_A and RAW_B as raw material to produce RAW_C. And, TASK_B
>> uses RAW_C and RAW_D as raw materials to produce the finished good.
>>
>>  Then I have created routing called RoutingA-B having routing task
>> A and B.
>>   Then I have created BOM for finished product only mentioning raw
>> materials RAW_A, RAW_B for sequence 1 and RAW_C and RAW_D for
>> sequence 2.
>>   Now creating a production run for finished product in jobshop it
>> does not shows the requirement for RAW_A and RAW_B.
>> Please suggest the way out...
>>
>> Enjoy Ofbiz
>> Brijesh M.
>> Jacopo Cappellato  wrote: Could you
>> please recreate this example in the demo server 
>> (https://demo.hotwaxmedia.com/manufacturing)?
>> I will try to have a quick look at it if you can do this.
>>
>> Jacopo
>>
>> On Jul 24, 2008, at 7:37 AM, brijesh m wrote:
>>
>>> Hi friends,
>>> I just want to accomplish one manufacturing process as follows :
>>>
>>>   A------------------------>B--------------------->Finished product
>>> (requries             (requires raw
>>> raw material        material as z
>>> x and y and         and w and
>>>  outputs z)           outputs finished
>>>                           product)
>>>
>>>
>>> here A and B are the routing tasks. What I have done is I have
>>> defined z as "work in progress" but when I create the production run
>>> for finished product it does not shows the requirement of x and y
>>> whether BOM is defined for finished product or for z and finished
>>> product both. Someone please share your thoughts on this.
>>>
>>>
>>> ENJOY Ofbiz
>>> Brijesh M.
>>>
>>>
>>>
>>
>>
>>
>
>
>



       

Reply via email to