Hi Jacopo, I have tried by this way also but when creating the production run for finished good it shows only the requirement of RAW_C and RAW_D but it has to show requirement for RAW_A and RAW_B to be effective. It shows that routing task A is needed but nothing else.
Thanks Brijesh M. Jacopo Cappellato <[EMAIL PROTECTED]> wrote: Your BOM is not setup correctly. You should have something like this: RAW_C | |________> RAW_A | |________> RAW_B FINISHED_GOOD | |________> RAW_C | |________> RAW_D The only one you have to define as WIP is RAW_C Jacopo On Jul 24, 2008, at 2:18 PM, brijesh m wrote: > Hi Jacopo, > I have created this example on : > https://demo.hotwaxmedia.com/manufacturing/control/main > here I have created > > Ram materials as RAW_A, RAW_B, RAW_D and RAW_C as work in progress. > I have created two routing tasks as TASK_A and TASK_B. Task_A > uses RAW_A and RAW_B as raw material to produce RAW_C. And, TASK_B > uses RAW_C and RAW_D as raw materials to produce the finished good. > > Then I have created routing called RoutingA-B having routing task > A and B. > Then I have created BOM for finished product only mentioning raw > materials RAW_A, RAW_B for sequence 1 and RAW_C and RAW_D for > sequence 2. > Now creating a production run for finished product in jobshop it > does not shows the requirement for RAW_A and RAW_B. > Please suggest the way out... > > Enjoy Ofbiz > Brijesh M. > Jacopo Cappellato wrote: Could you > please recreate this example in the demo server > (https://demo.hotwaxmedia.com/manufacturing)? > I will try to have a quick look at it if you can do this. > > Jacopo > > On Jul 24, 2008, at 7:37 AM, brijesh m wrote: > >> Hi friends, >> I just want to accomplish one manufacturing process as follows : >> >> A------------------------>B--------------------->Finished product >> (requries (requires raw >> raw material material as z >> x and y and and w and >> outputs z) outputs finished >> product) >> >> >> here A and B are the routing tasks. What I have done is I have >> defined z as "work in progress" but when I create the production run >> for finished product it does not shows the requirement of x and y >> whether BOM is defined for finished product or for z and finished >> product both. Someone please share your thoughts on this. >> >> >> ENJOY Ofbiz >> Brijesh M. >> >> >> > > >