Christian, To be correct: you don't need to do the 'dependent' production runs. That is a choice.
But yes, if you have specific tasks for the production of your sub-products you would be better of with specific production schemas. Otherwise, the 'default' schema will be used. Pierre Smits *ORRTIZ.COM <http://www.orrtiz.com>* Services & Solutions for Cloud- Based Manufacturing, Professional Services and Retail & Trade http://www.orrtiz.com On Tue, Jan 21, 2014 at 2:16 PM, Christian Carlow < [email protected]> wrote: > Thanks Pierre, > > To clarify, you're saying that the sub-products need their own separate > routing as well and using "dependent production run" will include those > sub-product routings? > > > On 01/21/2014 03:06 AM, Pierre Smits wrote: > >> Hi Christian, >> >> That is correct. If the end product consist of parts (sub products) that >> you produce also, you also need to have a bom and a production schema >> (with >> tasks and product association) for sub products. >> >> When creating a production run for the end product, you can automatically >> create the production runs for the sub products by setting the 'dependent >> production run' flag in the production run for the end product. >> >> Regards, >> >> Pierre Smits >> >> *ORRTIZ.COM <http://www.orrtiz.com>* >> >> Services & Solutions for Cloud- >> Based Manufacturing, Professional >> Services and Retail & Trade >> http://www.orrtiz.com >> >> >> On Tue, Jan 21, 2014 at 1:17 AM, Christian Carlow < >> [email protected]> wrote: >> >> When I run a production run routing for a product with BOM levels greater >>> than 1, the lower level materials are not listed in the Materials List >>> screenlet. Are separate routing required for each BOM level? >>> >>> For example, with BOM >>> part_1 >>> part_1_1 >>> rawpart_1_1 >>> part_1_2 >>> rawpart_1_2 >>> >>> I created a Routing called part_1 to which part_1 is linked as the >>> product. When I create a production run, only part_1_1 and part_1_2 are >>> listed as materials. Shouldn't rawpart_1_1 and rawpart_1_2 be listed in >>> the materials list also? I even linked routing tasks to the BOMs but it >>> didn't pull in the additional materials. >>> >>> >