Richard Barmann wrote:

Is there a Template or can you advise me on how to keep track of several houses under construction, They are all at different phases of completion.
Richard

How many houses have you got to deal with?

How do you assess how complete the houses are? Do you/are you able to express it as a percentage? If so, then you could just list all the houses in a column on Calc, then enter the percentage complete.

If assessing % complete is not convenient, you could establish a duration for each phase of each house's construction - eg:

prepare site, underground services, lay foundations: 3 weeks;
floor: 1 week;
wall frames: 3 weeks
roof and roof cladding: order and deliver trusses, 8 weeks from commencement;
roof cladding: 2 weeks
wall linings: 2 weeks
etc
etc

Then use a spreadsheet to list the activities in the first column, give each activity two rows, fill in the planned weeks like a bar/gantt chart with a fill colour and use the second of each activity's rows to mark actual progress. For example, use dark blue/light blue to show planned/actual progress.

You could set up each house on a separate sheet.

If that's not clear, I can construct and send you a sample directly if you want.

Regards

Adam

---------------------------------------------------------------------
To unsubscribe, e-mail: [EMAIL PROTECTED]
For additional commands, e-mail: [EMAIL PROTECTED]

Reply via email to