The FCC's One Touch Make Ready order doesn't apply in states where the state PSC governs pole attachments.  NY is one of those.

Welcome to the Evil Empire State.


On 1/3/2019 6:07 PM, [email protected] wrote:
Maybe it's time to send the pole owners a friendly reminder that the FCC's One 
Touch Make Ready order reaffirms  that attachers are not responsible for costs 
of repairing preexisting violations of safety or construction standards.

Jared

Sent: Thursday, January 03, 2019
From: "Adam Moffett" <[email protected]>
To: [email protected]
Subject: [AFMUG] Why some places don't have broadband yet

I just got a quote for make-ready on a 2 mile stretch.
$593,000