Oh I tried that one.
The FCC's One Touch Make Ready order doesn't apply in states where the
state PSC governs pole attachments. NY is one of those.
Welcome to the Evil Empire State.
On 1/3/2019 6:07 PM, [email protected] wrote:
Maybe it's time to send the pole owners a friendly reminder that the FCC's One
Touch Make Ready order reaffirms that attachers are not responsible for costs
of repairing preexisting violations of safety or construction standards.
Jared
Sent: Thursday, January 03, 2019
From: "Adam Moffett" <[email protected]>
To: [email protected]
Subject: [AFMUG] Why some places don't have broadband yet
I just got a quote for make-ready on a 2 mile stretch.
$593,000
I guess those 8 households will remain unserved because eff that.
--