Hello.

If time sheet for team members is entered in hours (e.g. 6 hours
monday, ..., 6 hours friday) and days are used as Time Estimation
Unit, agilo sums all hours of team members as days so in burndown
chart values for capacity can exceed 300, even if hours should be
converted to days.

I think that when entering Time Sheet for member there should be
comment that units entered are dependent on Time Estimation Unit so
label that states "Time Sheet (hours per day)" is not correct.

I would also like to ask how can I take in the account if some member
of the team is on vacation for one week of sprint. Currently I could
enter 0,66 for day fields and this would mean that in three week
sprint member will work 2/3. I am proposing following CR:
I. each week of sprint can have different values entered (so even one
day absence would be easily accomplished with entering 0 for such
day). Number of weeks/days in sprint can be easily calculated from
(FROM, TO) fields of sprint.
II. (LOW) If values for member in time sheet change currently only one
table exists "agilo_team_member". History about team avalability is
lost. It would be nice, if agilo_team_member would be connected with
sprint, so history would remain untouched for old sprints.


--~--~---------~--~----~------------~-------~--~----~
You received this message because you are subscribed to the Google
Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH 
http://www.agile42.com and is focused in supporting Agilo for Scrum users.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/agilo?hl=en
-~----------~----~----~----~------~----~------~--~---

Reply via email to