Agilo is very simple when it comes to the estimation unit as written in the admin page: "Please note that this setting only changes how time is displayed, the database is not updated automatically. If you switch from 'hours' to 'days' (or vice versa), a remaining time of '5h' will simply show up as '5d'."
Am 25.08.2009 17:52, schrieb tex:
If time sheet for team members is entered in hours (e.g. 6 hours monday, ..., 6 hours friday) and days are used as Time Estimation Unit,
Actually it is not like this. If you estimate in days, the daily capacity must be entered in days. If somewhere is still written hours, this is a display bug.
But agreed, it would be nice to have a bit more of "intelligence" :-) fs