Hello. I am using PRO 1.0.1 and am experiencing really weird behaviour
of sprint display window and burndown chart.

I. sum of remaining time
I have a sprint, that currently in progress and it contains stories
with following sum of story tasks:
story1: 5,5d
story2: 2,5d
story3: 5,5d
story4: 3,25d
stroy5: 3,5d
story6: 6,25d
story7: 3d
story8: 5d
If you sum up these remaining times you get 34,5d. But in sprint view
window Total (remaining time) shows 27.5d. Where does it come from?

II. burndown chart
There is also one issue with burdown chart for the same sprint. Spring
will end on 11. september and lasts 3 weeks (14 days). Initial sum of
stories was 39. Current is 34,5 as I already said. But the trend line
(red line on the chart) goes over 70 at the end of sprint, even if we
are moving tasks to done. See the link (must be concatenated):
img141.
imageshack.
us
/
img141
/
9389
/
burndown.png

I have following questions:
- why is my trend line going to 70d
- why doesn't my burndown chart start with value 39d
- why is my current burndown value not 34,5d

If someone can interpret such behaviour, I would really appreciate.
For the first problem I think it is a bug.

Thanks,
--~--~---------~--~----~------------~-------~--~----~
You received this message because you are subscribed to the Google
Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH 
http://www.agile42.com and is focused in supporting Agilo for Scrum users.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/agilo?hl=en
-~----------~----~----~----~------~----~------~--~---

Reply via email to