Can someone confirm, that this is a bug. It is also present in Agilo
PRO 1.0.2 version.

On Aug 27, 10:33 am, tex <[email protected]> wrote:
> Hello. I am using PRO 1.0.1 and am experiencing really weird behaviour
> of sprint display window and burndown chart.
>
> I. sum of remaining time
> I have a sprint, that currently in progress and it contains stories
> with following sum of story tasks:
> story1: 5,5d
> story2: 2,5d
> story3: 5,5d
> story4: 3,25d
> stroy5: 3,5d
> story6: 6,25d
> story7: 3d
> story8: 5d
> If you sum up these remaining times you get 34,5d. But in sprint view
> window Total (remaining time) shows 27.5d. Where does it come from?
>
> II. burndown chart
> There is also one issue with burdown chart for the same sprint. Spring
> will end on 11. september and lasts 3 weeks (14 days). Initial sum of
> stories was 39. Current is 34,5 as I already said. But the trend line
> (red line on the chart) goes over 70 at the end of sprint, even if we
> are moving tasks to done. See the link (must be concatenated):
> img141.
> imageshack.
> us
> /
> img141
> /
> 9389
> /
> burndown.png
>
> I have following questions:
> - why is my trend line going to 70d
> - why doesn't my burndown chart start with value 39d
> - why is my current burndown value not 34,5d
>
> If someone can interpret such behaviour, I would really appreciate.
> For the first problem I think it is a bug.
>
> Thanks,
--~--~---------~--~----~------------~-------~--~----~
You received this message because you are subscribed to the Google
Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH 
http://www.agile42.com and is focused in supporting Agilo for Scrum users.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/agilo?hl=en
-~----------~----~----~----~------~----~------~--~---

Reply via email to