- why is my trend line going to 70d - why doesn't my burndown chart start with value 39d
I guess that you added the tasks after the sprint started. So the first dot is the time exactly when the sprint started (unless you press 'confirm commitment'). The That's probably why the trend line sky-rockets.
Can you provide us with some db/environment where we can check the problem ourselves?