Hi,

We discussed this at the US National Committee of the IECEE on 19 April
2000.  There is some confusion on the interpretation of this requirement.
It was explained, that an amendment is NOT a correction or a change to a
part number.  An amendment is when new data/pages are added.  

Using Brent's example of adding an alternate plastic.  If no tests are
necessary, then it would not be an amendment.  If there was testing, then it
would be an amendment.

Ned Devine
Entela, Inc.
Program Manager III
Phone 616 248 9671
Fax  616 574 9752
e-mail  [email protected] 



-----Original Message-----
From: Matthew Meehan [mailto:[email protected]]
Sent: Thursday, May 11, 2000 1:35 AM
To: [email protected]
Subject: RE: Actual requirement or money making scheme?



Hi Brent,

> Subject: Actual requirement or money making scheme?

Definitely an actual requirement. (about the rest of your subject: No
comment).  

Decision:
Original CB Test Reports can be subjected to three (3) amendments only,
after
which a new CB Test Report and associate CB Test Certificate shall be
issued.
Explanatory notes:
Experience shows that by making more than three amendments to a CB
Test Report the technical features of the initial product becomes such
that the tracking against the Master File can be lost.

To get your very own copy go to:
http://www2.imq.it/ctldecisions/collect.htm
choose sheet 291 (bottom right)

Regards,
Matt

> Subject: Actual requirement or money making scheme?
> 
> 
> 
> Hello wise colleagues -
> 
> Just recently, we have decided to add some alternate components to one of
> our CB Reports and was informed by a particular agency that we needed to
> have a new CB Report issued since we already have 3 updates to the
existing
> report.
> 
> In the past, we were able to add an alternate plastic to the CB report and
> just pay for an addendum (few thousand...I know, I am already getting
ripped
> off).  But, now to add an alternate component and pay for a full CB Report
> and Certificate?!  That does not make sense.  After talking to the project
> engineer, he indicated that this is the direction of his organization and
> this interpretation will be implemented across the board with all member
> agencies.  We only have a few products with few changes.  I would hate to
> work for a computer manufacturer who changes the disk drive manufacturer
and
> model numbers like it was last month's model.  Oh yeah, it was last
month's
> model.
> 
> All I know is that this change in policy will push me well over budget
this
> year.  Without turning this into a bashing session of any particular
agency,
> can anyone direct me to an agency that has a more relaxed interpretation
of
> the "CB Update" requirement?
> 
> Thank you very much for your time and your expert advice.
> 
> Best Regards,
> Brent Taira
> 
> 
> -------------------------------------------
> This message is from the IEEE EMC Society Product Safety
> Technical Committee emc-pstc discussion list.
> 
> To cancel your subscription, send mail to:
>      [email protected]
> with the single line:
>      unsubscribe emc-pstc
> 
> For help, send mail to the list administrators:
>      Jim Bacher:              [email protected]
>      Michael Garretson:        [email protected]
> 
> For policy questions, send mail to:
>      Richard Nute:           [email protected]
> 
> 
> 

-------------------------------------------
This message is from the IEEE EMC Society Product Safety
Technical Committee emc-pstc discussion list.

To cancel your subscription, send mail to:
     [email protected]
with the single line:
     unsubscribe emc-pstc

For help, send mail to the list administrators:
     Jim Bacher:              [email protected]
     Michael Garretson:        [email protected]

For policy questions, send mail to:
     Richard Nute:           [email protected]


-------------------------------------------
This message is from the IEEE EMC Society Product Safety
Technical Committee emc-pstc discussion list.

To cancel your subscription, send mail to:
     [email protected]
with the single line:
     unsubscribe emc-pstc

For help, send mail to the list administrators:
     Jim Bacher:              [email protected]
     Michael Garretson:        [email protected]

For policy questions, send mail to:
     Richard Nute:           [email protected]

Reply via email to