Hello  Sir

In IEEE 57 bus, I fixed the capacity of transmission line and then increase the 
load and generation. I removed those lines whose power flow is more than their 
capacities. When the grid is divided into 4 parts. I remove the isolated buses. 
In island 1-------  45 buses are there including  7 generators. Matpower 
automatically considers the slack bus. But the DCOPF doesn't converge as the 
generation has a capacity of 1975.9 MW, but it dispatches only 928.9 MW. So 
there is a mismatch in load and generation. Load requirement is 1321.9 MW. Is 
there any mistake that I am doing? .