Ah, I see. Your error is that children should only be subtasks if they are
actually parts of their parent. Order supplies is not a part of decide
color, for example. So it should look like this:

Project: Paint truck red
     decide color....
     order supplies
     sand truck
     repair low spots
     apply primer
     resand

These are all sub-parts, components, of "Paint truck" but they are not
sub-parts of each other.

Then, either set "complete subtasks in order", which will make it so that
only the first one shows up on your lists (only the first will be Active),
or use a view that uses  Next Actions instead of all Active Actions.


>
> --