now i know why i got away from doing it this way

the 1st step if you will of first task in the list immediately goes "live"
 whether i want it to or not

the other way a next action would not appear on the list until i "started"
it

this way it's just there which means if i go thru my inbox and come up with
a whole bunch of next actions they are already in the to do list.

i guess i could only assign a context to the parent and children when i was
ready to start that particular project so that the "project category would
be more like the "outline" is and the the contexts would be the ones in play
at that moment.

hmmm have to think about this

On Fri, Sep 30, 2011 at 12:30 AM, Lisa Stroyan <[email protected]> wrote:

> Something must be set in your @office view. Make sure it's only set to show
> Active tasks.
>
> Lisa from mobile
> On Sep 29, 2011 1:41 PM, "daniel sekera" <[email protected]> wrote:
> > i understand what you are saying
> >
> > for a test i made a parent called paint truck
> > underneath i simply have step 1 step 2 and step 3
> >
> > i entered it as such
> >
> > paint truck
> > step1
> > step2
> > step3
> >
> > i have do subtasks in order checked on the parent and the context @office
> is
> > on all tasks
> >
> > i go to my to do list for the @office category and i have this
> >
> > step1
> > step2
> > step3
> >
> > which is not how i thought it should work it should have only been step1
> and
> > then when that gets completed step2 "appears" and so on
> >
> > this is why i got used to doing it
> >
> > step1
> > step2
> > step3
> >
> > because that way i will not get the next one until the bottom one is
> > completed. which is what is forcing me to have to enter my steps in
> reverse
> > order
> >
> > On Thu, Sep 29, 2011 at 11:52 AM, Lisa Stroyan <[email protected]>
> wrote:
> >
> >> Ah, I see. Your error is that children should only be subtasks if they
> are
> >> actually parts of their parent. Order supplies is not a part of decide
> >> color, for example. So it should look like this:
> >>
> >> Project: Paint truck red
> >> decide color....
> >> order supplies
> >> sand truck
> >> repair low spots
> >> apply primer
> >> resand
> >>
> >> These are all sub-parts, components, of "Paint truck" but they are not
> >> sub-parts of each other.
> >>
> >> Then, either set "complete subtasks in order", which will make it so
> that
> >> only the first one shows up on your lists (only the first will be
> Active),
> >> or use a view that uses Next Actions instead of all Active Actions.
> >>
> >>
> >>>
> >>> --
> >> Lisa Stroyan
> >> www.empathic-parenting.com
> >>
> >> --
> >> You received this message because you are subscribed to the Google
> Groups
> >> "MyLifeOrganized" group.
> >> To post to this group, send email to [email protected].
> >> To unsubscribe from this group, send email to
> >> [email protected].
> >> For more options, visit this group at
> >> http://groups.google.com/group/mylifeorganized?hl=en.
> >>
> >
> > --
> > You received this message because you are subscribed to the Google Groups
> "MyLifeOrganized" group.
> > To post to this group, send email to [email protected].
> > To unsubscribe from this group, send email to
> [email protected].
> > For more options, visit this group at
> http://groups.google.com/group/mylifeorganized?hl=en.
> >
>
> --
> You received this message because you are subscribed to the Google Groups
> "MyLifeOrganized" group.
> To post to this group, send email to [email protected].
> To unsubscribe from this group, send email to
> [email protected].
> For more options, visit this group at
> http://groups.google.com/group/mylifeorganized?hl=en.
>

-- 
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/mylifeorganized?hl=en.

Reply via email to