Re: [Axapta-Knowledge-Village] ended production orders

2008-03-26 Thread visti Sethna
Hi, The only way to do it is to make a rework order, in AX there is nothing called a rework order, but the only workaround will be to make a prod order of the quantity posted excess, remove the old BOM at production order level and in the BOM line only put the required quantity of the finished

Re: [Axapta-Knowledge-Village] Lead Time in planning for Scheduling of operations

2008-03-31 Thread visti Sethna
] *On Behalf Of *visti Sethna *Sent:* 31. marts 2008 07:35 *To:* Axapta-Knowledge-Village@yahoogroups.com *Subject:* [Axapta-Knowledge-Village] Lead Time in planning for Scheduling of operations Can someone tell me how will the time be captured for the subcontracting (Service type) item please

Re: [Axapta-Knowledge-Village] Lead Time in planning for Scheduling of operations

2008-04-01 Thread visti Sethna
is provided AS IS with no warranties, and confers no rights. *From:* visti Sethna [mailto:[EMAIL PROTECTED] *Sent:* 1. april 2008 07:11 *To:* Axapta-Knowledge-Village@yahoogroups.com; Anders Sorensen; thurmalla nagesh *Subject:* Re: [Axapta-Knowledge-Village] Lead Time in planning

[Axapta-Knowledge-Village] Pending Picking List

2008-04-02 Thread visti Sethna
Dear Friends Is it possible to print a consolidated list of all pending picking list journals. The report should give output sorted on the locations. Please reply coz this is urgent -- With Regards, Mr. Vishtaspa Sethna Associate E.R.P. Consultant Godrej Infotech Ltd. Cell: +919718010823

Re: [Axapta-Knowledge-Village] Re: Lead Time in planning for Scheduling of operations

2008-04-05 Thread visti Sethna
are C and D. I will send the material C and D to my vendor and in turn he will return me item A. -Tushar visti Sethna [EMAIL PROTECTED] wrote: Can someone tell me how will the time be captured for the subcontracting (Service type) item please. Coz My gant chart should capture the lead

[Axapta-Knowledge-Village] Urgent Help Required.

2008-04-17 Thread visti Sethna
Dear Mr. P. Bhatia / Dear Rajendra I am stuck up in posting production order operation wise. Coz when the journal gets generated, its not posting the operation time viz process time as per the route. ITs only creating a line for the set up time. Kindly let me knw what correctives to take in this

[Axapta-Knowledge-Village] How to Handle Rejections / Rework in Axapta

2008-05-03 Thread visti Sethna
Dear Friends Can you tell me how me map the Rejection / Rework, in AX. If there is a kind of Scenario where i have 4 or 5 operations in a route It is to be noted that the item code only changes after all the five operations are completed and not after each level. I need to reject an item at the

[Axapta-Knowledge-Village] Production Order To be Generated In Multiples - urgent

2008-05-17 Thread visti Sethna
Dear Friends, I am in need of some urgent help. Currently Master Planning is Generating orders based on requirement + safety stock. I need to generate certain orders in multiples. For Eg. a production order should always be generated in multiples of 5 for one quantity and in multiples of 7 for

Re: [Axapta-Knowledge-Village] Re: Production Order To be Generated In Multiples - urgent

2008-05-18 Thread visti Sethna
that i can show my technical team the same and help me achieve my deadline On 5/17/08, Mohamed [EMAIL PROTECTED] wrote: --- In Axapta-Knowledge-Village@yahoogroups.comAxapta-Knowledge-Village%40yahoogroups.com, visti Sethna Dear Friend, I would like to inform you that this case i faced

[Axapta-Knowledge-Village] Getting Sales Qotation Earliest Delivery Date from Master Planning

2008-05-18 Thread visti Sethna
Dear Friends, My client requires the following information. When he punches in a sales qotation with about 100 lines, master planning should give him the earliest delivery date of that qotation / inquiry depending upon the capacity avialable at the point of punching the qotation? Is this possible

[Axapta-Knowledge-Village] Accomodation of Urgent Order in Firmed Production Order

2008-05-18 Thread visti Sethna
Dear Friends, I require help on how to accomodate an urgent order that comes up after the production is firmed and scheduled for a month. If the delivery date of this new production order is much before the prior orders delivery date and it is an urgent order. How do I map the same in Master

[Axapta-Knowledge-Village] Capacity Adjustments on Work Centres.

2008-05-28 Thread visti Sethna
Dear Friends, I have a small querry to be addressed. I have a couple of production orders that are scheduled on various work centres in case of which I have my machines scheduled for a month or fortnight. Now there is an urgent production order that has to be executed in the middle of my

Re: [Axapta-Knowledge-Village] Re: Sales Forecasting

2008-06-20 Thread visti Sethna
Guys I have managed to set up the sales forecast and even intregrate it with the Master Planning, but am not able to reduce the forecast on basis of actual orders recieved neither is my orders firmed from forecast planning being taken into account for additional orders being generated on basis of

Re: [Axapta-Knowledge-Village] Problem occured during Master planning

2008-08-22 Thread visti Sethna
Dear NB When the orders are getting generated, go to inquiries and check the net requirements. You will mostly observev that the orders are getting generated due to the stock being insufficient to satisfy the entire demand for that particular item. Also go to the item master = Quantity Tab and

Re: [Axapta-Knowledge-Village] Problem occured during Master planning

2008-08-22 Thread visti Sethna
Dear Harry, This check box is turned on On Fri, Aug 22, 2008 at 8:18 PM, Harry Deshpande [EMAIL PROTECTED]wrote: Can you confirm that the 'on hand inventories' check box is turned on Regards harry *From:* Axapta-Knowledge-Village@yahoogroups.com [mailto: [EMAIL PROTECTED] *On

Re: [Axapta-Knowledge-Village] Exclude stock in Master Planning.

2008-10-07 Thread visti Sethna
Yes This kind of coverage is possible. In Inventory Management = Setup = Dimensions = Dimension Groups. Select you dimension group that you are using, Under storage dimensions activation setups = In overview tab, select Warehouse ( ensuring warehouse is active) In General Tab = Coverage,

[Axapta-Knowledge-Village] Urgent Querry

2008-11-05 Thread visti Sethna
Hi, See if anyone knows how to map this querry -- With Regards, Mr. Vishtaspa Sethna Associate E.R.P. Consultant Godrej Infotech Ltd. Cell: +919718010823

[Axapta-Knowledge-Village] Re: Urgent Querry

2008-11-05 Thread visti Sethna
Hi, See if anyone knows how to map this querry. I have a Shirt – This can be made from Cotton or Denim. Color can be Blue, Grey or Black Size: S, M, L, XL A shirt BOM will be 1) AAA Cloth - .75 mtrs. for S

[Axapta-Knowledge-Village] Editor Mumbai (Times of India)

2008-12-03 Thread visti Sethna
-- Forwarded message -- From: Sandeep Ghodvinde [EMAIL PROTECTED] Date: Wed, Dec 3, 2008 at 11:53 AM Subject: FW: Editor Mumbai (Times of India) To: Thanks and Regards Sandeep. -- *From:* Sumit Deshpande *Sent:* Wednesday, December 03, 2008 11:35

Re: [Axapta-Knowledge-Village] Production Order Costing Reversal

2009-02-17 Thread visti Sethna
Hey in what state is the production order, if it is not yet in started stage, you can redo the estimation stage for the production order. This should hopefully satisfy ur requirements. Do revert if u need anything else On Sat, Feb 14, 2009 at 10:35 AM, erp_1...@ymail.com erp_1...@ymail.comwrote:

Re: [Axapta-Knowledge-Village] Need help in Master Planning in AX9

2009-02-22 Thread visti Sethna
Hi, how do u enter Expected receipt for a month in which the plan is running and following 2 month =500 in the system, coz if u want this to be captured, you will have to tell the system about it. Let me know that and then I can guide you further On Fri, Feb 20, 2009 at 5:59 PM, ghoshsubhajit

Re: [Axapta-Knowledge-Village] Re: sub contracting process

2009-08-17 Thread visti Sethna
Hi Friends, I need one help in AX 2009. I need to map a subcontracting screnario in which i need to send a couple of items to the vendors, for painting. I need a few clarifications As this is a machine building scenario, there are almost 500 parts that need to go for painting to the vendor. 1)

Re: [Axapta-Knowledge-Village] Add-on for Meat Industry and Live Stock Management

2010-03-01 Thread visti Sethna
you can use a process industry vertical called fullscope. On 3/1/10, AX Consultant ax.consult...@yahoo.com wrote: Hi All, Is there is any add-on to AX2009 which related to the Meat Industry and Live Stock Management? Thanks, Mohamed Ismail a -- With Regards, Mr. Vishtaspa Sethna

Re: [Axapta-Knowledge-Village] PO and SO Numbers

2010-04-15 Thread visti Sethna
Hi Try to do a customisation using purchase and sales pools and fetch number sequence from the purchase and sales pools. you will need to select purchase / sales pool on the purchase / sales form first and then create the purchase / sales order. Or link the purchase / sales pool to the cust /

Re: [Axapta-Knowledge-Village] DEMO DATABASE

2010-04-25 Thread visti Sethna
Hi For food and beverage database please get the VPC for Process Vertical Full Scope. This has a data base which has some part of F/B and some part of chemicals. It may not satisfy you 100% but will help you to a great deal. Regards Visti On Fri, Apr 23, 2010 at 6:43 AM, Irshad

Re: [Axapta-Knowledge-Village] Re: Changing Units of Measure in AX2009

2010-09-03 Thread visti Sethna
-Knowledge-Village%40yahoogroups.com, visti Sethna visti2...@... wrote: static void TEC_UpdateInvent(Args _args) { InventTableModule inventTableModule; inventTable inventTable; ; ttsbegin; select forupdate inventTable where inventTable.ItemId == 'XXX