Re: Delaying 3.1 release by 2 to 3 weeks?
Ok, I've updated JIRA to list the release candidate build for Feb 3. Please submit the tests and documentation asap so that we can have sufficient review. I can always cut a release candidate before the 3rd, keep me posted on status. Patrick Mahadev Konar wrote: I think it should be done in 2 weeks.. mahadev On 1/16/09 2:34 PM, Patrick Hunt ph...@apache.org wrote: Mahadev, can you complete quotas in 2 weeks? This includes completing the code itself, documentation, tests, and incorporating review feedback? Parick Benjamin Reed wrote: we should delay. it would be good to try out quotas for a bit before we do the release. quotas are also a key part of the release. 3 weeks seem a little long though. ben From: Mahadev Konar [maha...@yahoo-inc.com] Sent: Thursday, January 15, 2009 4:32 PM To: zookeeper-dev@hadoop.apache.org Cc: zookeeper-u...@hadoop.apache.org Subject: Re: Delaying 3.1 release by 2 to 3 weeks? That was release 3.1 and not 3.2 :) mahadev On 1/15/09 4:26 PM, Mahadev Konar maha...@yahoo-inc.com wrote: Hi all, I needed to get quotas in zookeeper 3.2.0 and wanted to see if delaying the release by 2-3 weeks is ok with everyone? Here is the jira for it - http://issues.apache.org/jira/browse/ZOOKEEPER-231 Please respond if you have any issues with the delay. thanks mahadev
Re: Delaying 3.1 release by 2 to 3 weeks?
we should delay. it would be good to try out quotas for a bit before we do the release. quotas are also a key part of the release. 3 weeks seem a little long though. 3 weeks is just a worst case estimate... We should probably be done in 2 weeks. mahadev ben From: Mahadev Konar [maha...@yahoo-inc.com] Sent: Thursday, January 15, 2009 4:32 PM To: zookeeper-dev@hadoop.apache.org Cc: zookeeper-u...@hadoop.apache.org Subject: Re: Delaying 3.1 release by 2 to 3 weeks? That was release 3.1 and not 3.2 :) mahadev On 1/15/09 4:26 PM, Mahadev Konar maha...@yahoo-inc.com wrote: Hi all, I needed to get quotas in zookeeper 3.2.0 and wanted to see if delaying the release by 2-3 weeks is ok with everyone? Here is the jira for it - http://issues.apache.org/jira/browse/ZOOKEEPER-231 Please respond if you have any issues with the delay. thanks mahadev
Re: Delaying 3.1 release by 2 to 3 weeks?
Mahadev, can you complete quotas in 2 weeks? This includes completing the code itself, documentation, tests, and incorporating review feedback? Parick Benjamin Reed wrote: we should delay. it would be good to try out quotas for a bit before we do the release. quotas are also a key part of the release. 3 weeks seem a little long though. ben From: Mahadev Konar [maha...@yahoo-inc.com] Sent: Thursday, January 15, 2009 4:32 PM To: zookeeper-dev@hadoop.apache.org Cc: zookeeper-u...@hadoop.apache.org Subject: Re: Delaying 3.1 release by 2 to 3 weeks? That was release 3.1 and not 3.2 :) mahadev On 1/15/09 4:26 PM, Mahadev Konar maha...@yahoo-inc.com wrote: Hi all, I needed to get quotas in zookeeper 3.2.0 and wanted to see if delaying the release by 2-3 weeks is ok with everyone? Here is the jira for it - http://issues.apache.org/jira/browse/ZOOKEEPER-231 Please respond if you have any issues with the delay. thanks mahadev
Re: Delaying 3.1 release by 2 to 3 weeks?
I think it should be done in 2 weeks.. mahadev On 1/16/09 2:34 PM, Patrick Hunt ph...@apache.org wrote: Mahadev, can you complete quotas in 2 weeks? This includes completing the code itself, documentation, tests, and incorporating review feedback? Parick Benjamin Reed wrote: we should delay. it would be good to try out quotas for a bit before we do the release. quotas are also a key part of the release. 3 weeks seem a little long though. ben From: Mahadev Konar [maha...@yahoo-inc.com] Sent: Thursday, January 15, 2009 4:32 PM To: zookeeper-dev@hadoop.apache.org Cc: zookeeper-u...@hadoop.apache.org Subject: Re: Delaying 3.1 release by 2 to 3 weeks? That was release 3.1 and not 3.2 :) mahadev On 1/15/09 4:26 PM, Mahadev Konar maha...@yahoo-inc.com wrote: Hi all, I needed to get quotas in zookeeper 3.2.0 and wanted to see if delaying the release by 2-3 weeks is ok with everyone? Here is the jira for it - http://issues.apache.org/jira/browse/ZOOKEEPER-231 Please respond if you have any issues with the delay. thanks mahadev
Re: Delaying 3.1 release by 2 to 3 weeks?
That was release 3.1 and not 3.2 :) mahadev On 1/15/09 4:26 PM, Mahadev Konar maha...@yahoo-inc.com wrote: Hi all, I needed to get quotas in zookeeper 3.2.0 and wanted to see if delaying the release by 2-3 weeks is ok with everyone? Here is the jira for it - http://issues.apache.org/jira/browse/ZOOKEEPER-231 Please respond if you have any issues with the delay. thanks mahadev