This may be a good application for cable bracing. Contact Loos Co. 
(www.earthquakebrace.com)  and pose the question to them.


At 06:57 PM 7/1/2010, you wrote:
>Hello Sprinklerforum,
>
>   I am looking for ways to put longitudinal bracing on a straight 
> run of 6" Schedule 40 pipe that can expand or contract About 5" 
> with a temperature swing from 40 degrees to 100 degrees. This is a 
> 1400' durn near straight run. I am looking at using a Metraflex 
> Building Separation loop for an expansion loop.
>
>--
>Best regards,
>Charles Thurston
>Coastal Fire Protection                          mailto:[email protected]
>
>_______________________________________________
>Sprinklerforum mailing list
>[email protected]
>http://fireball.firesprinkler.org/mailman/listinfo/sprinklerforum
>
>For Technical Assistance, send an email to: [email protected]
>
>To Unsubscribe, send an email to:[email protected]
>(Put the word unsubscribe in the subject field)

Todd G. Williams, PE
Fire Protection Design/Consulting
Stonington, CT
860.535.2080
www.fpdc.com

_______________________________________________
Sprinklerforum mailing list
[email protected]
http://fireball.firesprinkler.org/mailman/listinfo/sprinklerforum

For Technical Assistance, send an email to: [email protected]

To Unsubscribe, send an email to:[email protected]
(Put the word unsubscribe in the subject field)

Reply via email to