Dear Taverna developers,

We are still working on the formal semantics and were not entirely  
sure about the exact semantics of control links. We currently have two  
guesses:

If there is a link from processor P to Q then
1. Q cannot start any activity
2. Q cannot start consuming any of its input
until P has completely produced its output.

Is it 1 or 2? They are not exactly the same since Q might have some  
parts that already are able to execute without needing any input.

Kind regards,

-- Jan Hidders


------------------------------------------------------------------------------
Crystal Reports - New Free Runtime and 30 Day Trial
Check out the new simplified licensing option that enables unlimited
royalty-free distribution of the report engine for externally facing 
server and web deployment.
http://p.sf.net/sfu/businessobjects
_______________________________________________
taverna-hackers mailing list
[email protected]
Web site: http://www.taverna.org.uk
Mailing lists: http://www.taverna.org.uk/taverna-mailing-lists/
Developers Guide: http://www.mygrid.org.uk/tools/developer-information

Reply via email to