Yes there is a javascript error on the sprint backlog view: Error: subview.setSubviews is not a function Source File: http://project.pqa.local/trac/nzert/chrome/agilo/js/backlogView.js Line: 187
I found a reference to this bug a few months back and the suggestion was to be sure there were not issues with linking tickets that contained 'remaining time' - I removed the remaining time field from some ticket types and now only tasks have remaining time. This didn't fix the issue. Thanks, -Craig On May 14, 10:11 am, Martin Häcker <[email protected]> wrote: > Hi Craig, > > Am 12.05.10 03:11, schrieb Craig Griffin: > > > > > I'm having a blank background on certain sprint backlogs in the new > > backlog. Felix suggested I post to the group as a whole. Backlogs work > > fine in the old view. Not every backlog has this problem, however we > > have eliminated every link between tickets with remaining hours so > > that only tasks have hours. This did not fix the problem. > > > Am 11.05.2010 03:29, schrieb Craig Griffin: > > > I'm having the same problem and I see the original person never > > responded, so I will. I'm having the same problem, new backlog is > > blank, old backlog is fine. I'm especially worried because the > > next > > release doesn't have the old backlog anymore, and we'd be in BIG > > trouble without being able to see our sprint backlog. > > > this sounds a bit worrying for sure and I'd like to make sure that the > > Sprint backlog still works in this case. > > Definitely, so lets try and debug the problem. > > Could you please check if you see any javascript exceptions when loading > the backlog? (Firebug or the Safari Debugger work great for this). > > Not seeing a backlog at all could only be caused by js exceptions I > think - or maybe by a backlog name that defeats agilos escaping and is > therefore not found on the server (though that also should show a clear > error). > > Regards, > Martin > > -- > -- > Follow Agilo on Twitter:http://twitter.com/agiloforscrum > Please support us by reviewing and voting > on:http://userstories.com/products/8-agilo-for-scrumhttp://ohloh.net/p/agilo-scrumhttp://freshmeat.net/projects/agiloforscrum > > You received this message because you are subscribed to the Google > Groups "Agilo for Scrum" group. This group is moderated by agile42 > GmbHhttp://www.agile42.comand is focused in supporting Agilo for Scrum > users.To post to this group, send email [email protected] > To unsubscribe from this group, send email > [email protected] > For more options, visit this group > athttp://groups.google.com/group/agilo?hl=en -- -- Follow Agilo on Twitter: http://twitter.com/agiloforscrum Please support us by reviewing and voting on: http://userstories.com/products/8-agilo-for-scrum http://ohloh.net/p/agilo-scrum http://freshmeat.net/projects/agiloforscrum You received this message because you are subscribed to the Google Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH http://www.agile42.com and is focused in supporting Agilo for Scrum users. To post to this group, send email to [email protected] To unsubscribe from this group, send email to [email protected] For more options, visit this group at http://groups.google.com/group/agilo?hl=en