I am tired just reading about your progress.  Makes my basement door thing 
seem pathetically small in comparison.

I dug a hole in the bottom of the pit on Sunday.  I sunk a large plastic 
sump into the hole.  I dumped a bunch of gravel at the bottom of this 
secondary hole, punched a bunch of holes in the bottom of the plastic sump 
and placed the sump into the hole and dumped a bit more gravel into the 
sump to weight it down a bit and keep it from shifting too much.

There is a lid on the sump and there will be a drain passing through the 
cement slab and draining into the sump.

There will also be some of that 4 inch perforated pipe running around the 
outside of the pit and dumping into the sump.  This will hopefully keep 
the pit reasonably dry except in the case of continuous rain for several 
days.

Now I just have to haul all the cement up the stairs and I can pour the 
slab.

Then I'll just have to haul all the cement blocks up the stairs and build 
the walls of the pit.


-- 