At 08:36 PM 7/15/2003, David Abrahams wrote:

>Beman Dawes <[EMAIL PROTECTED]> writes:
>
>...
>
>> Hum... You must be seeing some way of getting a 1.30.1 release out
>> that eludes me. What would go into 1.30.1?
>
>Exactly what's on the end of the RC_1_30_0 branch plus whatever
>additional small fixes were deemed important and can be applied in a
>day or two; release to happen in a week.

Ah! That is much more doable.

>> Who will act as release manager?
>
>I guess I'd have to reluctantly volunteer, now that I've suggested it.

Sounds like you just talked your way into a new job:-)

So a schedule might look something like the following?

   -- 1.30.1 - Selected bug fixes only (details up to release manager).
               Schedule: a week or two from now

   -- 1.31.0 - New library, breaking interface changes, many fixes.
               Schedule: TBA, but work is basically already well underway.

--Beman