Hi Barton, although vague (it all depends on what you consider as medium
sized CMS implementation) here it goes my answer.

Having stated and froze requirements, I would risk to say that that it
would take between 2-5 months to have the system running with no
problems (I mean working as predicted and required by users, including
training).

But because frozen requirements never exist I would risk 3-6 months.

Complex CMS's implementations take around 1-1.5 year (in stages to 3-4
months).

Easy usually implementations take 0.5-2 months.

Then again this all depends what you believe it's an easy, medium or
complex CMS implementation, and what is a completed CMS implementation.

This are not estimates for your implementation (I have no knowledge
about your requirements, technology, analysis, nothing to do such
estimate). They are just some pointers.

Best regards,

Nuno Lopes
Independent Consultant


--