For Hope Creek


1) Does your facility use "Trip Tickets" to access the RRA/RCA?

Yes required for all workers including RP

If so,

A) How many levels or types of tickets based on type of work or activity to be 
performed are used?

Just one level of tickets.  Multiple levels of tickets gets confusing.



B) What type of radiological briefing is given for each level, (for example 
self-briefed or RP briefed)?



We have a sign-off for the RP tech if a High Rad Briefing is performed as well 
as a electronic sign off acknowledging the brief when RWP is signed into.



(2)  How are work control and the "dose budget" integrated into the RRA/RCA 
access process?

In p3 / now P6 every work activity has dose associated with the activity.  As 
long as the worker signs into the RWP with the right work order activity end of 
day reports allow each task to be evaluated for dose performance.



A)     How is the dose budget maintained and updated?



RP has a document that is updated every morning prior to 0600 for online.  
ALARA performs every 4 hours during an outage