PMBOK Section: Estimate Activity Durations
Process Group: Planning Process Group
Question Type: Calculation
Knowledge Area: Time Management
Difficulty Level: Moderate
*Question*: "You are managing a construction project. You are currently
estimating the duration of a very critical activity. You have gathered the
following information from the experts:
Best case scenario: Activity can take 3 days to complete.
Worst case scenario: Activity may take up to 12 days to complete.
Expected scenario: On average it takes up to 6 days to complete such
activities.
What will be standard deviation of the activity?"
A. 1.25 days
B. 1.5 days
C. 1 day
D. Cannot be determined by the data given.
Hint : Use PERT to find the standard deviation.
Reference: PMP Study Guide 5ed - Sybex - pg:170
*Explanation*: Standard deviation formula for PERT (triangular
distribution) is (Pessimistic-Optimistic)/6. The standard deviation of the
given data, according to this formula, is 1.5 days. Hence choice B is the
correct answer
------------------------------
All our free questions are updated to the latest *PMBOK® Guide* standard. Sign
up here to receive the questions via
email<http://www.free-pm-exam-questions.com>.
We are a PMI Registered Education Provider.
Until next time,
Cornelius Fichtner, PMP
*Explanation*: Standard deviation formula for PERT (triangular
distribution) is (Pessimistic-Optimistic)/6. The standard deviation of the
given data, according to this formula, is 1.5 days. Hence choice B is the
correct answer.
--
You received this message because you are subscribed to the Google Groups
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to
[email protected].
For more options, visit this group at
http://groups.google.com/group/project-managment?hl=en.