All,

The following PMP® exam sample question is taken from
http://www.free-pm-exam-questions.com - The answer is at the very bottom:


------------------------------

PMBOK Section: Estimate Activity Durations

Process Group:     Planning Process Group


Question Type:     Calculation

Knowledge Area: Time Management

Difficulty Level:   Moderate





*Question*: "You are managing a construction project. You are currently
estimating the duration of a very critical activity. You have gathered the
following information from the experts:

Best case scenario: Activity can take 3 days to complete.

Worst case scenario: Activity may take up to 12 days to complete.

Expected scenario: On average it takes up to 6 days to complete such
activities.



What will be standard deviation of the activity?"



            A.        1.25 days


            B.        1.5 days


            C.        1 day


            D.        Cannot be determined by the data given.



Hint :   Use PERT to find the standard deviation.


Reference: PMP Study Guide 5ed - Sybex - pg:170



*Explanation*:   Standard deviation formula for PERT (triangular
distribution) is (Pessimistic-Optimistic)/6. The standard deviation of the
given data, according to this formula, is 1.5 days. Hence choice B is the
correct answer

------------------------------


All our free questions are updated to the latest *PMBOK® Guide* standard. Sign
up here to receive the questions via
email<http://www.free-pm-exam-questions.com>.
We are a PMI Registered Education Provider.


Until next time,
Cornelius Fichtner, PMP















*Explanation*:   Standard deviation formula for PERT (triangular
distribution) is (Pessimistic-Optimistic)/6. The standard deviation of the
given data, according to this formula, is 1.5 days. Hence choice B is the
correct answer.

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/project-managment?hl=en.

Reply via email to