All, The following PMP® exam sample question is taken from http://www.free-pm-exam-questions.com - The answer is at the very bottom:
------------------------------ PMBOK Section: Sequence Activities Process Group: Planning Process Group Question Type: Calculation Knowledge Area: Time Management Difficulty Level: Moderate Question: "Activity / Duration / Predecessor A / 4 / START B / 3 / A C / 1 / B D / 5 / START E / 4 / D F / 6 / E G / 2 / C,F H / 4 / D I / 2 / H What is the duration of the critical path?" A. 10 B. 11 C. 17 D. 18 Hint : Use PDM to calculate. Reference: PMBOK4 – pg:138 ------------------------------ All our free questions are updated to the latest *PMBOK® Guide* standard. Sign up here to receive the questions via email<http://www.free-pm-exam-questions.com>. We are a PMI Registered Education Provider. Until next time, Cornelius Fichtner, PMP The Project Management PrepCast™ – <http://www.project-management-prepcast.com/> http://www.project-management-prepcast.com The Project Management Podcast™ – <http://www.project-management-podcast.com/> http://www.project-management-podcast.com The answer is C. Explanation: The duration of the critical path for the given data is 17. Hence choice C is correct while rest of the choices are incorrect. -- You received this message because you are subscribed to the Google Groups "project managment" group. To post to this group, send email to [email protected]. To unsubscribe from this group, send email to [email protected]. For more options, visit this group at http://groups.google.com/group/project-managment?hl=en.
