The following PMP® exam sample question is taken from
http://www.free-pm-exam-questions.com - The answer is at the very bottom:


------------------------------
PMBOK Section: Sequence Activities
Process Group: Planning Process Group
Question Type: Calculation
Knowledge Area: Time Management
Difficulty Level: Moderate

Question: "Activity / Duration / Predecessor

A / 4 / START
B / 3 / A
C / 1 / B
D / 5 / START
E / 4 / D
F / 6 / E
G / 2 / C,F
H / 4 / D
I / 2 / H

What is the duration of the critical path?"

A. 10
B. 11
C. 17
D. 18

Hint : Use PDM to calculate.
Reference: PMBOK4 – pg:138

------------------------------


All our free questions are updated to the latest *PMBOK® Guide* standard. Sign
up here to receive the questions via
email<http://www.free-pm-exam-questions.com>.
We are a PMI Registered Education Provider.

Until next time,
Cornelius Fichtner, PMP
The Project Management PrepCast™ –
<http://www.project-management-prepcast.com/>
http://www.project-management-prepcast.com
The Project Management Podcast™ –
<http://www.project-management-podcast.com/>
http://www.project-management-podcast.com






The answer is C.
Explanation: The duration of the critical path for the given data is 17.
Hence choice C is correct while rest of the choices are incorrect.

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/project-managment?hl=en.

Reply via email to