How do you mean "Skipped", as in just not completed?  If this is the case then 
the Change Status will not change to completed as a default behavior.

Ron Taylor

From: [email protected]
To: [email protected]
Subject: [servman] - Skip last Activity - Change does not Complete
Date: Tue, 28 May 2013 12:23:24 +0000









Hi,
 
we have found the following issue:
 
when within a Change Request the last activity will be “Skipped” – the Change 
Status does not get “Completed” if all other activities where “Completed”.
Within Service Requests this works fine. 

 
Does anyone know what the behavior should be?
Should a CR be “Completed” if all Activities are Completed and the last one is 
“Skipped”?
 
Thanks!
 
-Peter
 
                                          