when I first started, it was Dinasaur skins and charcoal.
 
 
 
 
> Date: Tue, 11 Nov 2008 12:02:26 -0800> From: [EMAIL PROTECTED]> To: 
> [email protected]> Subject: Re: LAK OF CO-ORDINATION> > 
> Craig,> > When I first started we drew pictures in the dirt with a stick.> 
> Personally all I'd like to see is some coordination. Five recent> projects, 
> all remodels:> > First project; (Fire Detection/Bidding documents for 
> contractor design> project) Backgrounds are essentially floor plans with some 
> equipment> drawn in but most of that unlabeled so that you have to guess 
> whether> something is an architectural feature, equipment on the floor, or> 
> equipment tall enough to be in the way. The Architect wants detailed> 
> drawings as to conduit runs on a bidder layout conceptual design.> 
> Essentially this is the design an undefined system within an partially> 
> defined space.> > Second project: (Sprinkler/Shop drawings) The A&E provides 
> a full set> of drawings, water data, detailed drawing of where the mains are 
> to> run, design criteria, notes as to where auxiliary dry systems are to> be 
> located to cover unheated turret attics, etc. I need to do detail> layout for 
> the winning contractor.> > Third project: (Sprinkler/Constructibility study): 
> I get detailed, in> progress drawings and have to design a system in 
> sufficient detail to> prove constructibility. The Architect rotates the 
> ceiling grid 90> degrees after I've laid out heads and piping. I submit a 
> change order> and get paid.> > Fourth project: (Sprinkler/Contractor design) 
> Design criteria from A&E> is for contractor to put in a system complying with 
> applicable rules.> I request full CAD drawings. A&E refuses on grounds of 
> "intellectual> property" and sends selected (his not mine) pdfs.> > Fifth 
> project: (Sprinkler/Contractor design)) I get CAD plans but> Architect has 
> drawn everything on a single layer.> > Grade this as you see fit but I give 
> initially a D to number one until> they requested detail drawings at which 
> time they fell to F-. Number> two gets an A for providing the needed 
> information vis-a-vis the level> of effort they asked from me. Number three 
> gets a B because the> otherwise C work (asking for a final design before 
> their own design> was finalized) was saved by the extra credit associated 
> with paying me> without a fight for their mistake. Number four is a D because 
> of the> intellectual property BS. This is a remodel. What am I going to do> 
> with their architectural plan? For that matter what am I going to do> with 
> any one off building architectural plan? The design cost more> than it 
> otherwise would because I had to reproduce, rather than clean> up the CAD 
> drawings. Five gets a B since it was essentially a hand> drawing for 
> practical purposes but had all the necessary info.> > And finally a sixth 
> project--Commissioning team. Very large project> that had very few conflicts 
> that weren't caught and corrected before> they became major battles. An A- 
> only because it could have gone> smoother with more cooperation from the 
> owner (who acted as his own> AHJ) and architect who interfered with the 
> commissioning process far> too often in the name of haste.> > On Tue, Nov 11, 
> 2008 at 11:22 AM, <[EMAIL PROTECTED]> wrote:> > So if you could have your 
> say, what would be the desired deliverable from the AE? Would you want to see 
> a pile of drawings, a CD full of drawings, a walk through of the building via 
> some 3D magic or what?> >> > 3D cad hasn't been around forever, when I first 
> started in this business it was ink on mylar and you got copies of everyone 
> else's drawings to do your coordination. The only computers were on the 
> Starship Enterprise.> >> >> > Craig L. Prahl, CET> > Fire Protection 
> Specialist> > Mechanical Department> > CH2MHILL> > Lockwood Greene> > 1500 
> International Drive> > PO Box 491, Spartanburg, SC 29304-0491> > Direct - 
> 864.599.4102> > Fax - 864.599.8439> > [EMAIL PROTECTED]> > 
> http://www.ch2m.com> >> >> > -----Original Message-----> > From: [EMAIL 
> PROTECTED] [mailto:[EMAIL PROTECTED] On Behalf Of Thom McMahon> > Sent: 
> Tuesday, November 11, 2008 1:54 PM> > To: [email protected]> > 
> Subject: RE: LAK OF CO-ORDINATION> >> > This is typically what we all see. 
> "Sprinkler shall co-ordinate with all trades" MEANING "If I get here first 
> you'll have to move even if your drawings are the only ones that give 
> elevation and distance off walls and column lines"> >> > Remember when we 
> used to get "Duct Shop Drawings" that had duct sizes, BOD (bottom of duct) 
> showed where they were off of the structure in feet and inches. Now every 
> duct guy just installs off the MPE drawings with no elevations or set 
> distances, just because it's on cad. It leaves you to guess if his fittings 
> are FOB (Flat on Top) or FOB (Flat on Bottom) Why are there more change 
> orders? Because the engineering community hasn't increased their Level of 
> Care, to reflect that their bid drawings are now the shop drawings for the 
> MPE trades.> >> > Yeah we all hear the 3D will make this change order thing 
> go away, just like a "Paperless society" Computers and printers have only 
> made more paper usage easier. When was the last time you bought a printer 
> that printed fewer pages per min than the one it replaced? More paper + more 
> CYA, so when in double print it out, in case the computer crashes. 3D can 
> help with co-ordination, but only to the level of expertise of the person 
> inputting the data. Usually a IT geek or nerd, not the PE, and rarely anyone 
> with actual hands on experience of how it really goes together.> >> > Thom 
> McMahon, SET> > Firetech, Inc.> > 2560 Copper Ridge Dr> > P.O. Box 882136> > 
> Steamboat Springs, CO 80488> > Tel: 970-879-7952> > Fax: 970-879-7926> >> >> 
> >> > (sprinkler) can go around us. It's like a 3D retrofit. The only thing 
> that changes is we spend more design time to come up with the same product.> 
> > Besides we FP contractors have been doing 3D since the beginning of time, 
> it's just that the presentation has been 2D.> >> > Ron Fletcher> > Aero 
> Automatic> > Phoenix, AZ> >> > 
> _______________________________________________> > Sprinklerforum mailing 
> list> > http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum> > For 
> Technical Assistance, send an email to: [EMAIL PROTECTED]> >> > To 
> Unsubscribe, send an email to:[EMAIL PROTECTED]> > (Put the word unsubscribe 
> in the subject field)> > _______________________________________________> > 
> Sprinklerforum mailing list> > 
> http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum> > For 
> Technical Assistance, send an email to: [EMAIL PROTECTED]> >> > To 
> Unsubscribe, send an email to:[EMAIL PROTECTED]> > (Put the word unsubscribe 
> in the subject field)> >> > > > -- > Ron Greenman> at home....> 
> _______________________________________________> Sprinklerforum mailing list> 
> http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum> For Technical 
> Assistance, send an email to: [EMAIL PROTECTED]> > To Unsubscribe, send an 
> email to:[EMAIL PROTECTED]> (Put the word unsubscribe in the subject 
> field)_______________________________________________
Sprinklerforum mailing list
http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum
For Technical Assistance, send an email to: [EMAIL PROTECTED]

To Unsubscribe, send an email to:[EMAIL PROTECTED]
(Put the word unsubscribe in the subject field)

Reply via email to