Steve and others, 

 

Thank you for your responses.

 

Does anyone have or heard of Failure Rates related to Schedule 10 steel pipe. I 
am not talking about MIC or Corrosion failures. I am dealing with a large 
customer with many properties all with sprinkler systems, new and existing who 
is not allowing schedule 10. These are not dry pipe system failures either.

 

I am going to try and meet with this owner’s representative to hear his 
concerns directly. It would be great if I could present some facts to him.

 

Regards,

G. Tim Stone

 

G. Tim Stone Consulting, LLC

NICET Level III Engineering Technician

Fire Protection Sprinkler Design

and Consulting Services

 

   117 Old Stage Rd. - Essex Jct., VT. 05452

                 CELL: (802) 373-0638  

             [email protected] <mailto:[email protected]> 

 

From: Steve Leyton <[email protected]> 
Sent: Tuesday, November 22, 2022 1:47 PM
To: Discussion list on issues relating to automatic fire sprinklers 
<[email protected]>
Subject: [Sprinklerforum] Re: Steel pipe failure rates

 

We’ve seen our first pieces of Sch. 10 fail from MIC recently, but that’s a 
different ballgame and NONE of the parent steel alloys factor that in their CRR 
ratings.   I’d like offer another angle if I may, because this thread has been 
in the context of contractor and product practices only so far.   Please keep 
in mind that for the owner of a building, there’s more to issues like this than 
just means and methods. 

 

We are the EOR and specifier for a LOT of publicly bid work, and for our 
institutional clients have been specifying 10 and 40 only for 25 year.   I’m 
sure that Sch. 7 advocates won’t necessarily like or agree with that approach, 
but unlike most consulting engineering firms, we have NEVER been the target of 
a claim or lawsuit.  In fact, we’ve only had to put our insurance company on 
notice of a potential claim one time in 27 years.   Needless to say, I’m proud 
of that of record and from our current perspective if it ain’t broke don’t fix 
it. 

 

I want to emphasize that there is NOTHING wrong with Sch. 7 and I’m not 
suggesting that it’s inferior.  When I was in contracting, we used a lot of 
Sch. 7.  In fact, I still remember the day that a rep from American Tube & 
Conduit brought in a piece of DynaFlow for the first time – we were amazed.  
But the fact is that this material is more subject to oxygen cell corrosion and 
MIC.  As a consultant, corrosion control service provider and also as an expert 
witness, I’ve managed and observed the removal of a lot of leaky pipes over the 
years and have only seen Sch. 7 being subject to the various types of 
irreparable damage that necessitates R&R.   

 

If maintained at a high level from the time it’s commissioned into service, 
there’s no reason not to use it but… that’s the wildcard.   Developers and 
owners of the built environment seem to only hate one thing more than fire 
sprinklers, and that’s having to ITM their fire sprinklers.   Until such time 
as we can say that our universal sprinklered environment is aggressively 
maintained in good condition, this issue will not go away and it’s fair for 
owners to acknowledge the realities of the situation and specify 10 and 40 
only, IMHO.

 

 

Steve Leyton, President

Protection Design and Consulting

T  |  619.255.8964 x 102  |   <http://www.protectiondesign.com/> 
www.protectiondesign.com 
2851 Camino Del Rio South  |  Suite 210  |  San Diego, CA  92108
Fire Protection System Design | Consulting | Planning | Training

 

 

 

 

From: [email protected] <mailto:[email protected]>  <[email protected] 
<mailto:[email protected]> > 
Sent: Tuesday, November 22, 2022 10:14 AM
To: 'Discussion list on issues relating to automatic fire sprinklers' 
<[email protected] 
<mailto:[email protected]> >
Subject: [Sprinklerforum] Re: Steel pipe failure rates

 

Only that the owner is worried about pipe failures using schedule 10. I don’t 
know where is information is coming from. In my 34 years in this industry I 
have never heard or seen Schedule 10 pipe failures on water filled sprinkler 
systems unless they freeze. The only other scenario is the use of Schedule 10 
on dry pipe systems which we all are learning is for the short term unless you 
are charging that pipe with Nitrogen.

 

Regards,

G. Tim Stone

 

G. Tim Stone Consulting, LLC

NICET Level III Engineering Technician

Fire Protection Sprinkler Design

and Consulting Services

 

   117 Old Stage Rd. - Essex Jct., VT. 05452

                 CELL: (802) 373-0638  

             [email protected] <mailto:[email protected]> 

 

From: Fpdcdesign <[email protected] <mailto:[email protected]> > 
Sent: Tuesday, November 22, 2022 1:01 PM
To: Discussion list on issues relating to automatic fire sprinklers 
<[email protected] 
<mailto:[email protected]> >
Subject: [Sprinklerforum] Re: Steel pipe failure rates

 

Did the specifying engineer state why he/she wants only Sch 40?

 

 

On Nov 22, 2022 at 12:14 PM, <Skyler Bilbo <mailto:[email protected]> > 
wrote:

I always use the Corrosion Resistance Ratio (CRR) argument.  Basically, the 
thickness of schedule 10 piping is greater than or equal to the thickness of 
the first exposed thread of threaded schedule 40.  Using this argument, 
schedule 10 should theoretically last at least as long as threaded schedule 40. 
 You can't use this argument if they call for grooved schedule 40.

 

 

Thanks,


Skyler Bilbo

  
<https://linkprotect.cudasvc.com/url?a=https%3a%2f%2fci3.googleusercontent.com%2fmail-sig%2fAIorK4y8Hq3kJpcrMKcZPAe4JT4xB7a2Rf10HH9h91m15sYft0q0IkyUaWivqrU3_iQPJ9vznaW8t_4&c=E,1,yEA4GFaGWfku4hxN2FHeDjcyE0Od8owVOIzks_AMeV9rVyhPTFQOWdVEDdwi05pAHS9NWpUL6_jMN7nFO6-2y3Kt7gZq0-Q2Huryuqg-g0z5rt1RiQzQGtlWd2Eg&typo=1>
 

1700 S. Raney Street

Effingham, IL 62401

217-819-6404 Direct

217-347-7315 Fax

 

[email protected] <mailto:[email protected]> 

www.wenteplumbing.com 
<https://linkprotect.cudasvc.com/url?a=http%3a%2f%2fwww.wenteplumbing.com&c=E,1,tqcCTUvTsVZ3GxrxQwwnJS5PiAdOLl2-h5687N6OeKBS_QefaDkU9H_TjiNVFd77lsU4n1Dj4JHMXQ1ydiJQnvIABPNXx85WkDcEvzxXO8NC5bWFobILpDM6x02K&typo=1>
 

 

 

On Tue, Nov 22, 2022 at 10:14 AM <[email protected] 
<mailto:[email protected]> > wrote:

Are there any studies comparing the failure rates of Schedule 10 steel pipe 
versus schedule 40 steel pipe used on wet water filled sprinkler systems?

I have a client who is not allowing the use of schedule 10 Main piping 2 ½” and 
larger on their projects. All piping used has to be schedule 40.

 

Thank you in advance.

 

Regards,

G. Tim Stone

 

G. Tim Stone Consulting, LLC

NICET Level III Engineering Technician

Fire Protection Sprinkler Design

and Consulting Services

 

   117 Old Stage Rd. - Essex Jct., VT. 05452

                 CELL: (802) 373-0638  

             [email protected] <mailto:[email protected]> 

 


_________________________________________________________
SprinklerForum mailing list:
https://lists.firesprinkler.org/list/sprinklerforum.lists.firesprinkler.org 
<https://linkprotect.cudasvc.com/url?a=https%3a%2f%2flists.firesprinkler.org%2flist%2fsprinklerforum.lists.firesprinkler.org&c=E,1,-cZa30wgEkO0P4nNy4MvQmtJ5Kvt2m3NH76I1XXz1F3O49Qy6BdnzcMA2n2BdHPHeR5PN3fZiKrgAp1koErvohrDAfW2SnBn-lJoa-3e-VESVpegmmQK&typo=1>
 
To unsubscribe send an email to [email protected] 
<mailto:[email protected]> 

_________________________________________________________ SprinklerForum 
mailing list: 
https://lists.firesprinkler.org/list/sprinklerforum.lists.firesprinkler.org 
<https://linkprotect.cudasvc.com/url?a=https%3a%2f%2flists.firesprinkler.org%2flist%2fsprinklerforum.lists.firesprinkler.org&c=E,1,xoOClOg0q-fIYBWwurjfS4bjkgLSDROGVvdFzz6h6VUxTWkoQKC-AnK4spRU89pMADppifeIAKTpepLp1gSREOhNkpb4N_oYtHtrqKKsXxoUNJm7&typo=1>
  To unsubscribe send an email to [email protected] 
<mailto:[email protected]> 

_________________________________________________________
SprinklerForum mailing list:
https://lists.firesprinkler.org/list/sprinklerforum.lists.firesprinkler.org
To unsubscribe send an email to [email protected]

Reply via email to