The following PMP® exam sample question is taken from
http://www.free-pm-exam-questions.com - The answer is at the bottom:


On Friday March 25, 2011 we will be launching a new PMP Exam Simulator at
http://www.pm-exam-simulator.com. You can receive 20% discount if you sign
up to our launch newsletter

------------------------------
PMBOK Section: Plan Communications
Process Group: Planning Process Group
Question Type: Calculation
Knowledge Area: Communications Management
DifficultyLevel:Hard

Question: "You are managing a telecom project. You have got two teams
reporting to you. One team is responsible for equipment installation and the
other team is responsible to commission and test that equipment. Both teams
are working in parallel such that as soon as the installation teams finishes
equipment installation at one site they move on to another site for
installations and the commissioning and testing team start their activities
on the newly installed site. The reporting structure is such that each of
the teams have 5 engineers headed by a team lead. Each team member interacts
with each other, however only the team leads interact with you. Both the
team leads also interact with each other to synchronize their operations.


How many communication channels do you have in your project?"

A. 33

B. 23

C. 42

D. 78


Hint: Calculate communication channels for each team and add them together
Reference: PMBOK4 pg:253

Explanation: This was a hard question, wasn't it? Lets analyze the scenario
to calculate the answer. Here we have two independent teams. Each team has 6
members, i.e., 5 engineers and one team lead. Each team member is
interacting with each other, so communication channels for each team are
(6)(6-1)/2=15. Both the team leads are communicating with you so there are
two communication channels for this interaction. Further since both the team
leads are interacting with each other there is an another communication
channel between them. Hence the total communication channels in your project
is 15+15+2+1=33.

------------------------------


All our free questions are updated to the latest PMBOK® Guide standard. Stop
by at http://www.free-pm-exam-questions.com to receive the questions via
email. We are a PMI Registered Education Provider.


Until next time,
Cornelius Fichtner, PMP
The Project Management PrepCast™ -
http://www.project-management-prepcast.com
The Project Management Podcast™ - http://www.project-management-podcast.com
Choice A is the only correct answer to this question.

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/project-managment?hl=en.

Reply via email to