Hi All,

The following PMP® exam sample question is taken from The Free PMP Exam
Simulator at http://free.pm-exam-simulator.com - The answer is at the very
bottom:

------------------------------

You are the project manager of a dress manufacturing company. You have been
asked to estimate for a project that requires you to create 500 shirts. You
know from experience that since the time required by a person to create a
shirt is 8 hours, the total effort required would be 4000 person hours.
Which estimation technique are you using here?

A) Analogous
B) Bottom up
C) Three point
D) Parametric

------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by
at http://free.pm-exam-simulator.com and try The PMP Exam Simulator free for
3 days. We also offer 110 free questions at
http://www.free-pm-exam-questions.com. We are a PMI Registered Education
Provider.


Until next time,
Cornelius Fichtner, PMP
The Project Management PrepCastTM -
http://www.project-management-prepcast.com
The Project Management PodcastTM - http://www.project-management-podcast.com







The Correct Answer is D

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/project-managment?hl=en.

Reply via email to