The following PMP® exam sample question is taken from The Free PMP Exam Simulator at http://free.pm-exam-simulator.com<http://www.linkedin.com/redirect?url=http%3A%2F%2Ffree%2Epm-exam-simulator%2Ecom&urlhash=728Q&_t=tracking_anet>- The answer is at the very bottom:
------------------------------ Which of the following may be considered as the outputs of performing Quality Assurance? A) Requested changes, recommended corrective actions, organizational process assets, project management plan. B) Requested changes, requested preventive actions, Quality metrics C) Quality management plan, Quality metrics, Quality baseline D) Quality control measurements, recommended preventive actions ------------------------------ All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com<http://www.linkedin.com/redirect?url=http%3A%2F%2Ffree%2Epm-exam-simulator%2Ecom&urlhash=728Q&_t=tracking_anet>and try The PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com<http://www.linkedin.com/redirect?url=http%3A%2F%2Fwww%2Efree-pm-exam-questions%2Ecom&urlhash=Juw9&_t=tracking_anet>. We are a PMI Registered Education Provider. Until next time, Cornelius Fichtner, PMP The Project Management PrepCast™ - http://www.project-management-prepcast.com<http://www.linkedin.com/redirect?url=http%3A%2F%2Fwww%2Eproject-management-prepcast%2Ecom&urlhash=U9sZ&_t=tracking_anet> The Project Management Podcast™ - http://www.project-management-podcast.com<http://www.linkedin.com/redirect?url=http%3A%2F%2Fwww%2Eproject-management-podcast%2Ecom&urlhash=lkMj&_t=tracking_anet> The Correct Answer is A. -- You received this message because you are subscribed to the Google Groups "project managment" group. To post to this group, send email to [email protected]. To unsubscribe from this group, send email to [email protected]. For more options, visit this group at http://groups.google.com/group/project-managment?hl=en.