PMBOK Section: Perform Quantitative Risk
Analysis

Process Group:     Planning Process
Group

Question Type:     Calculation

Knowledge Area:  Risk Management

Difficulty Level:
Easy


*Question*: A risk has a potential impact of $50,000 if it happens. The
probability of the occurrence of this risk is 50%. What is the expected
value for this risk?



            A.
100000

            B.
75000

            C.
-50000

            D.
-25000



Hint: Calculate the expected value by EMV formula. Also note that threats
are treated as negative
numbers.


Reference: PMBOK4 - pg:298


------------------------------


All our questions are updated to the latest PMBOK® Guide standard. Stop by
at http://free.pm-exam-simulator.com and try it for 3 days. We are a PMI
Registered Education Provider.



Until next time,
Cornelius Fichtner, PMP
The Project Management PrepCast™ -
http://www.project-management-prepcast.com
The Project Management Podcast™ - http://www.project-management-podcast.com

*Explanation*: EMV for a risk is calculated by multiplying the value of its
impact by its probability of occurrence. This will result in -$25,000.
Choice D is the correct answer to this question

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/project-managment?hl=en.

Reply via email to