Hello Wrenches,

An off grid, Radian / Mate 3 system we set up some years back has worked flawlessly. The client is now reporting that his system will only go into absorption charge for 1 hour per calendar day. The setting was previously to absorb for 2 hours.

He has tried shutting off the generator and then restarting. The inverter will connect, but not go into absorb.

During this cloudy period, he is only able to get the batteries to about 80 percent before he needs to leave the site for a week or so.

I finally go through to Outback, and they think it is a Firmware problem. As it is a long drive out, it seems worth while to run it by the list. Does FW this seem like the issue?

Thank you,

Drake

--
_______________________________________________
List sponsored by Redwood Alliance

List Address: RE-wrenches@lists.re-wrenches.org

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

There are two list archives for searching. When one doesn't work, try the other:
https://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/
http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
http://www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
http://www.members.re-wrenches.org

Reply via email to