Has anyone run into a case where the AHJ requires a special inspection
form filled for when the interstitial space is filled entirely with
non-combustible insulation?
It is fairly common in this area for Type V construction multi-family
projects to have the interstitial spaces, and sometimes flat attic
spaces, to be filled entirely with non-combustible insulation in lieu of
providing fire sprinklers in the area. However, we have one local AHJ
that is mandating this is a condition that requires a special inspection
form. It's a done deal because he flat out stated that it is our way
and this is how it will be. I just wonder if anyone else has run into
this. We are in the process of investigating what all is required. It
seems that we will need a professional engineer to go out and sign off
that all insulation is filling the cavity entirely.
--
Travis Mack, SET
MFP Design, LLC
2508 E Lodgepole Drive
Gilbert, AZ 85298
480-505-9271
fax: 866-430-6107
email:[email protected]
http://www.mfpdesign.com
https://www.facebook.com/pages/MFP-Design-LLC/92218417692
Send large files to us via: https://www.hightail.com/u/MFPDesign
LinkedIn: https://www.linkedin.com/in/travismack
---
This email has been checked for viruses by AVG.
http://www.avg.com
_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org