Hi Giulio,

You can use the "supplies wood Y" as a BOM (Manufacturing Bill of
Materials). It depends on how much quantity of BOM's use to Manufacturing
the X product as well as use the Production Run between the time of
Manufacturing the X product (finished good). It's depend on the status of
Production Run.
-> If BOM not available in a stock Production run in creating status.
-> If BOM available in stock Production run in process status.
-> The production run is closed after X product (finished good) is ready.
The total cost of Manufacturing the X product is based on Unit Cost of BOM
'S and quantity to be used for Manufactured the X product.

Thanks & Regards,
Karam

Reply via email to