Glen Garside has the correct notion: it depends ... on the
standard(s) used for the evaluation and the application
within the equipment.  The anticipated installation
environment must certainly play a role in just how intensely
reliable an earthing connection needs to be.

The general philosophy is to maintain a reliable earthing
interconnection system.  The reliability must be maintained
during normal operation, service, maintenance or repair of
the equipment.  It can be thought similar to hanging a "do
not disturb" sign on a hotel door.  How this may be achieved
is not normally prescribed in standards and one must apply
common sense and ignore common cents (which is the normal
driver for reducing the number of earthing studs).

In my opinion, it is desirable for every earthing connection
to have a separate termination, but this is not always
practical or even necessary.

There are instances where PE connections are reliably
maintained, even when stacked.  For instance, equipment
using two detachable power supply cordsets, where the
appliance inlets are in proximity to one another.  Inlets
are not normally removed for service, maintenance or repair
functions, so there is little reason to despair at using a
single stud.

On the other hand, if the inlets are not proximate to one
another, separate studs represent best practice, since PE
connections should be brought to the chassis as close as
practicable to where the supply conductors enter the
equipment.

Where the equipment is hard wired, as is the case for most
NEBS environment equipment, a separate PE terminal for each
supply is requisite.  Where installation codes in the US and
Canada apply, separate PE terminals are required.

Other considerations would have to include equipment where
such high secondary circuit currents flow that failure to
maintain tight equipotential bonding within the equipment
can cause significant interoperability issues.  In such
cases, though, studs may be a poor choice and ground bars
and similar devices are better suited to the task.



Regards,

Peter L. Tarver, PE
Product Safety Manager
Sanmina-SCI Homologation Services
San Jose, CA
[email protected]



This message is from the IEEE EMC Society Product Safety
Technical Committee emc-pstc discussion list.

Visit our web site at:  http://www.ewh.ieee.org/soc/emcs/pstc/

To cancel your subscription, send mail to:
     [email protected]
with the single line:
     unsubscribe emc-pstc

For help, send mail to the list administrators:
     Ron Pickard:              [email protected]
     Dave Heald:               [email protected]

For policy questions, send mail to:
     Richard Nute:           [email protected]
     Jim Bacher:             [email protected]

Archive is being moved, we will announce when it is back on-line.
All emc-pstc postings are archived and searchable on the web at:
    http://www.ieeecommunities.org/emc-pstc

Reply via email to