Hello All,

First thing is that the Infrastructure Change Approver role is only
necessary in case of Group Approval. If you are using Individual
approvers then Infrastructure Change Approver role is not required. But
still it will not affect the Approval process.

One more thing is that you will not be able to change the status of previous
Change tickets having this 
problem. You need to create another test tickets to check this.

Also if you are using your own Approval Process Definitions (i.e. Other
than Global) then you need to check that definitions. 

For more information you can use Approval Server Guide for Users and
Administrators.

Hope this will help you


lann wrote:
 
 For the Assignee the Status field is Disabled.Iam trying to go to the
 next Status Request For Change .
 There are no pending approvals required ,so I feel the assignee can do the
 Status change,I clicked Approve in the Process Flow accelerator and did
 a Save.But no Status change happened.
 
 Lann
 
 
 J.T. Shyman wrote:
 
 What do you mean by unable to move...? Is there an error message or is
 the
 status field disabled?
 
 --- J.T. Shyman
 
  -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 7:46 AM
 To: arslist@ARSLIST.ORG
 Subject: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 Iamstuck with a problem
 
 The assignee and manager of a Change Request are unable to move the
 Change
 ticket's Status beyond Request For Authorization. 
 I ensure the following:
 Assigne ehas  Infrastructure Change Assignee role-Fixed Permission. 
 Availability is Yes 
 No approvers in Review Phase. 
 Added the assignee as Adhoc approver and tried ,but in vain
  
 Any other configuration I missed out?
 Any ideas will be greatly appreciated.
 Thx
 Lann
 
 -- 
 View this message in context:
 http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-Reque
 st-For-Authorization.-tp17775621p17775621.html
 Sent from the ARS (Action Request System) mailing list archive at
 Nabble.com.
 
 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 
 
 

-- 
View this message in context: 
http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-Request-For-Authorization.-tp17775621p17857879.html
Sent from the ARS (Action Request System) mailing list archive at Nabble.com.

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are


Re: Can't move the Change ticket's Status beyond Request For Authorization.

2008-06-14 Thread lann
Thanks Lisa.
The approval process definitions are OTB ones and no change has been made to
them.

For Request For Authorization Status -Phase-(Review Phase)
The definition is as follows:
Review Phase
Approved-Request For Change
Rejected-Request For Authorization
No Approvers-Request For Change

I even tried out giving Infrastructure Change Approver permission for the
manager and Assignee,
still a mystery 

Lann

LisaD wrote:
 
 Sorry to jump in so late, but I would probably check the Approval
 Process Mappings and see what status you have set to move to if there
 are no approvers.  This is where you can set the status defaults for
 each stage.
 
 Also, if there is a 'Business Approval' stage/phase, and there are no
 approvers defined, the change remains in Request for Change status and
 requires the Change Manager or Change Assignee to move the change
 forward.  (Sounds like you may have already tried this one.)
 
 Also, if you want to run an arlog I would be happy to look at it to see
 why the status isn't changing.
 
 Thanks,
 LisaD
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Friday, June 13, 2008 7:42 AM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 There are no approvers displayed in the approal tab at all.
 
 lann
 
 Decou, Candace M wrote:
 
 Oh and also they should have the role for Infrastructure Change
 Approver
 as well I think.
 :)
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 10:10 PM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 For the Assignee and Manager the Status field is Disabled.Iam trying
 to go
 to the next Status Request For Change .
 There are no pending approvals required ,so I feel the
 assignee/manager
 can
 do the Status change,I clicked Approve in the Process Flow
 accelerator
 and
 did a Save.But no Status change happened.
 
 Lann
 
 
 Decou, Candace M wrote:
 
 I think the Change Manager assignee needs to move the Change Request
 forward.  So, in other words, if I read this right, the Change
 Assignee
 is trying to move it forward but it requires some action on the part
 of
 one of the CAB members (Change Manager assignee).  Who is that person
 or
 group?  Try having them select 'Approve' then move on to the next
 stage
 and see if that helps.
 :)
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of J.T. Shyman
 Sent: Wednesday, June 11, 2008 4:54 AM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 What do you mean by unable to move...? Is there an error message or
 is
 the
 status field disabled?
 
 --- J.T. Shyman
 
  -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 7:46 AM
 To: arslist@ARSLIST.ORG
 Subject: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 Iamstuck with a problem
 
 The assignee and manager of a Change Request are unable to move the
 Change
 ticket's Status beyond Request For Authorization. 
 I ensure the following:
 Assigne ehas  Infrastructure Change Assignee role-Fixed
 Permission. 
 Availability is Yes 
 No approvers in Review Phase. 
 Added the assignee as Adhoc approver and tried ,but in vain
  
 Any other configuration I missed out?
 Any ideas will be greatly appreciated.
 Thx
 Lann
 
 -- 
 View this message in context:


 http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-R
 eque
 st-For-Authorization.-tp17775621p17775621.html
 Sent from the ARS (Action Request System) mailing list archive at
 Nabble.com.
 


 
 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 


 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist

Re: Can't move the Change ticket's Status beyond Request For Authorization.

2008-06-13 Thread lann
Hi,
  For sure I logged in as the ticket's assignee/manager and they had
respective roles Infrastructure Change Assignee/Infrastructure Change
Manager respectively.
Availability is Yes and are in a group.

Lann

Decou, Candace M wrote:
 
 But when 'you' did this, were you logged in as someone in the group for
 Change Assignee, or as someone in the group for Change Manager?  Also,
 are you or is this person who is attempting this set up with appropriate
 roles for the group to include Infrastructure Change Manager?  It could
 be that you don't have the proper 'roles' or groups set for yourself?
 This is just a guess.  The people who you set up as Change Managers must
 be in the Change Management group (whatever you are calling it) and they
 must also have the Infrastructure Change Manager role assigned and they
 must also be set to Available.
 Keep us posted - I am making certain assumptions here on the setup in
 your environment, so not sure if I am hitting the mark for you or not.
 :) 
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 10:10 PM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 For the Assignee and Manager the Status field is Disabled.Iam trying
 to go
 to the next Status Request For Change .
 There are no pending approvals required ,so I feel the assignee/manager
 can
 do the Status change,I clicked Approve in the Process Flow accelerator
 and
 did a Save.But no Status change happened.
 
 Lann
 
 
 Decou, Candace M wrote:
 
 I think the Change Manager assignee needs to move the Change Request
 forward.  So, in other words, if I read this right, the Change
 Assignee
 is trying to move it forward but it requires some action on the part
 of
 one of the CAB members (Change Manager assignee).  Who is that person
 or
 group?  Try having them select 'Approve' then move on to the next
 stage
 and see if that helps.
 :)
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of J.T. Shyman
 Sent: Wednesday, June 11, 2008 4:54 AM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 What do you mean by unable to move...? Is there an error message or
 is
 the
 status field disabled?
 
 --- J.T. Shyman
 
  -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 7:46 AM
 To: arslist@ARSLIST.ORG
 Subject: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 Iamstuck with a problem
 
 The assignee and manager of a Change Request are unable to move the
 Change
 ticket's Status beyond Request For Authorization. 
 I ensure the following:
 Assigne ehas  Infrastructure Change Assignee role-Fixed
 Permission. 
 Availability is Yes 
 No approvers in Review Phase. 
 Added the assignee as Adhoc approver and tried ,but in vain
  
 Any other configuration I missed out?
 Any ideas will be greatly appreciated.
 Thx
 Lann
 
 -- 
 View this message in context:

 http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-R
 eque
 st-For-Authorization.-tp17775621p17775621.html
 Sent from the ARS (Action Request System) mailing list archive at
 Nabble.com.
 

 
 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 

 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 

 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 
 
 -- 
 View this message in context:
 http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-R
 equest-For-Authorization.-tp17775621p17792536.html
 Sent from the ARS (Action Request System) mailing list archive at
 Nabble.com

Re: Can't move the Change ticket's Status beyond Request For Authorization.

2008-06-13 Thread lann
There are no approvers displayed in the approal tab at all.

lann

Decou, Candace M wrote:
 
 Oh and also they should have the role for Infrastructure Change Approver
 as well I think.
 :)
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 10:10 PM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 For the Assignee and Manager the Status field is Disabled.Iam trying
 to go
 to the next Status Request For Change .
 There are no pending approvals required ,so I feel the assignee/manager
 can
 do the Status change,I clicked Approve in the Process Flow accelerator
 and
 did a Save.But no Status change happened.
 
 Lann
 
 
 Decou, Candace M wrote:
 
 I think the Change Manager assignee needs to move the Change Request
 forward.  So, in other words, if I read this right, the Change
 Assignee
 is trying to move it forward but it requires some action on the part
 of
 one of the CAB members (Change Manager assignee).  Who is that person
 or
 group?  Try having them select 'Approve' then move on to the next
 stage
 and see if that helps.
 :)
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of J.T. Shyman
 Sent: Wednesday, June 11, 2008 4:54 AM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 What do you mean by unable to move...? Is there an error message or
 is
 the
 status field disabled?
 
 --- J.T. Shyman
 
  -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 7:46 AM
 To: arslist@ARSLIST.ORG
 Subject: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 Iamstuck with a problem
 
 The assignee and manager of a Change Request are unable to move the
 Change
 ticket's Status beyond Request For Authorization. 
 I ensure the following:
 Assigne ehas  Infrastructure Change Assignee role-Fixed
 Permission. 
 Availability is Yes 
 No approvers in Review Phase. 
 Added the assignee as Adhoc approver and tried ,but in vain
  
 Any other configuration I missed out?
 Any ideas will be greatly appreciated.
 Thx
 Lann
 
 -- 
 View this message in context:

 http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-R
 eque
 st-For-Authorization.-tp17775621p17775621.html
 Sent from the ARS (Action Request System) mailing list archive at
 Nabble.com.
 

 
 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 

 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 

 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 
 
 -- 
 View this message in context:
 http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-R
 equest-For-Authorization.-tp17775621p17792536.html
 Sent from the ARS (Action Request System) mailing list archive at
 Nabble.com.
 
 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 

-- 
View this message in context: 
http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-Request-For-Authorization.-tp17775621p17822505.html
Sent from the ARS (Action Request System) mailing list archive at Nabble.com.

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: Where

Re: Can't move the Change ticket's Status beyond Request For Authorization.

2008-06-13 Thread Lisa Westerfield
Sorry to jump in so late, but I would probably check the Approval
Process Mappings and see what status you have set to move to if there
are no approvers.  This is where you can set the status defaults for
each stage.

Also, if there is a 'Business Approval' stage/phase, and there are no
approvers defined, the change remains in Request for Change status and
requires the Change Manager or Change Assignee to move the change
forward.  (Sounds like you may have already tried this one.)

Also, if you want to run an arlog I would be happy to look at it to see
why the status isn't changing.

Thanks,
LisaD

-Original Message-
From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of lann
Sent: Friday, June 13, 2008 7:42 AM
To: arslist@ARSLIST.ORG
Subject: Re: Can't move the Change ticket's Status beyond Request For
Authorization.

There are no approvers displayed in the approal tab at all.

lann

Decou, Candace M wrote:
 
 Oh and also they should have the role for Infrastructure Change
Approver
 as well I think.
 :)
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 10:10 PM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 For the Assignee and Manager the Status field is Disabled.Iam trying
 to go
 to the next Status Request For Change .
 There are no pending approvals required ,so I feel the
assignee/manager
 can
 do the Status change,I clicked Approve in the Process Flow
accelerator
 and
 did a Save.But no Status change happened.
 
 Lann
 
 
 Decou, Candace M wrote:
 
 I think the Change Manager assignee needs to move the Change Request
 forward.  So, in other words, if I read this right, the Change
 Assignee
 is trying to move it forward but it requires some action on the part
 of
 one of the CAB members (Change Manager assignee).  Who is that person
 or
 group?  Try having them select 'Approve' then move on to the next
 stage
 and see if that helps.
 :)
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of J.T. Shyman
 Sent: Wednesday, June 11, 2008 4:54 AM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 What do you mean by unable to move...? Is there an error message or
 is
 the
 status field disabled?
 
 --- J.T. Shyman
 
  -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 7:46 AM
 To: arslist@ARSLIST.ORG
 Subject: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 Iamstuck with a problem
 
 The assignee and manager of a Change Request are unable to move the
 Change
 ticket's Status beyond Request For Authorization. 
 I ensure the following:
 Assigne ehas  Infrastructure Change Assignee role-Fixed
 Permission. 
 Availability is Yes 
 No approvers in Review Phase. 
 Added the assignee as Adhoc approver and tried ,but in vain
  
 Any other configuration I missed out?
 Any ideas will be greatly appreciated.
 Thx
 Lann
 
 -- 
 View this message in context:


http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-R
 eque
 st-For-Authorization.-tp17775621p17775621.html
 Sent from the ARS (Action Request System) mailing list archive at
 Nabble.com.
 



 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 



 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 



 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 
 
 -- 
 View this message in context:

http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-R
 equest-For-Authorization.-tp17775621p17792536.html
 Sent from the ARS (Action Request System) mailing list archive

Re: Can't move the Change ticket's Status beyond Request For Authorization.

2008-06-13 Thread Decou, Candace M
Yes - good point, we didn't ask whether any of the approval process
mappings have been changed or if they are as is out-of-box.  But I still
think you need to specify that the Change Manager has role of Change
Approver - even if they are not specified as an approver in the Approval
tab, they still may need that role permission to 'Approve' the request
in this sense in order to move it along.  Anyway, it wouldn't hurt to
give the  Change Management Approval role to the Change Manager - try it
again and see if that works.
Lisa - am I wrong on this?
:)  

Candace DeCou

DOI Remedy Systems Analyst 
Verizon Business 
Office:  (408) 371-1112

Email: [EMAIL PROTECTED] 

 

Verizon Business - global capability, personal accountability. 

This e-mail is strictly confidential and intended only for use by the
addressee unless otherwise indicated

-Original Message-
From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of Lisa Westerfield
Sent: Friday, June 13, 2008 7:07 AM
To: arslist@ARSLIST.ORG
Subject: Re: Can't move the Change ticket's Status beyond Request For
Authorization.

Sorry to jump in so late, but I would probably check the Approval
Process Mappings and see what status you have set to move to if there
are no approvers.  This is where you can set the status defaults for
each stage.

Also, if there is a 'Business Approval' stage/phase, and there are no
approvers defined, the change remains in Request for Change status and
requires the Change Manager or Change Assignee to move the change
forward.  (Sounds like you may have already tried this one.)

Also, if you want to run an arlog I would be happy to look at it to see
why the status isn't changing.

Thanks,
LisaD

-Original Message-
From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of lann
Sent: Friday, June 13, 2008 7:42 AM
To: arslist@ARSLIST.ORG
Subject: Re: Can't move the Change ticket's Status beyond Request For
Authorization.

There are no approvers displayed in the approal tab at all.

lann

Decou, Candace M wrote:
 
 Oh and also they should have the role for Infrastructure Change
Approver
 as well I think.
 :)
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 10:10 PM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 For the Assignee and Manager the Status field is Disabled.Iam trying
 to go
 to the next Status Request For Change .
 There are no pending approvals required ,so I feel the
assignee/manager
 can
 do the Status change,I clicked Approve in the Process Flow
accelerator
 and
 did a Save.But no Status change happened.
 
 Lann
 
 
 Decou, Candace M wrote:
 
 I think the Change Manager assignee needs to move the Change Request
 forward.  So, in other words, if I read this right, the Change
 Assignee
 is trying to move it forward but it requires some action on the part
 of
 one of the CAB members (Change Manager assignee).  Who is that person
 or
 group?  Try having them select 'Approve' then move on to the next
 stage
 and see if that helps.
 :)
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of J.T. Shyman
 Sent: Wednesday, June 11, 2008 4:54 AM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 What do you mean by unable to move...? Is there an error message or
 is
 the
 status field disabled?
 
 --- J.T. Shyman
 
  -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 7:46 AM
 To: arslist@ARSLIST.ORG
 Subject: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 Iamstuck with a problem
 
 The assignee and manager of a Change Request are unable to move the
 Change
 ticket's Status beyond Request For Authorization. 
 I ensure the following:
 Assigne ehas  Infrastructure Change Assignee role-Fixed
 Permission. 
 Availability is Yes 
 No approvers in Review Phase. 
 Added the assignee as Adhoc approver and tried ,but in vain
  
 Any other configuration I missed out?
 Any ideas will be greatly appreciated

Re: Can't move the Change ticket's Status beyond Request For Authorization.

2008-06-13 Thread Lisa Westerfield
Regarding Functional Roles:  All they should need is the Infrastructure
Change Assignee role or the Infrastructure Change Manager role in order
to move this change forward.

Also - 
I just went back and read where you stated that the Status field is
disabled.  This is eerily similar to an issue I experienced during my
first Change implementation.  We found a couple of problems during
troubleshooting, so maybe I should take you down that path as well.  The
tool obviously thinks that there is an approval necessary at this point,
which is why the status field is disabled, so let's try this:

1.  We found a problem with the approval process not running completely
- To verify that the Approval Server is running, or to audit Approval
Server activity, you can turn on Approval Server logging in
AP:Administration form to check this.  
2.  If you are using the OOTB approval process configurations, which
process name are you using (for example: Change Level CI - Business).  I
can compare these administration settings to what I have OOTB to see if
there are any differences.
3.  What are the phases in your approval process configuration, where
the starting phase is Request for Authorization?

Thanks,
Lisa

-Original Message-
From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of Decou, Candace M
Sent: Friday, June 13, 2008 11:11 AM
To: arslist@ARSLIST.ORG
Subject: Re: Can't move the Change ticket's Status beyond Request For
Authorization.

Yes - good point, we didn't ask whether any of the approval process
mappings have been changed or if they are as is out-of-box.  But I still
think you need to specify that the Change Manager has role of Change
Approver - even if they are not specified as an approver in the Approval
tab, they still may need that role permission to 'Approve' the request
in this sense in order to move it along.  Anyway, it wouldn't hurt to
give the  Change Management Approval role to the Change Manager - try it
again and see if that works.
Lisa - am I wrong on this?
:)  

Candace DeCou

DOI Remedy Systems Analyst 
Verizon Business 
Office:  (408) 371-1112

Email: [EMAIL PROTECTED] 

 

Verizon Business - global capability, personal accountability. 

This e-mail is strictly confidential and intended only for use by the
addressee unless otherwise indicated

-Original Message-
From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of Lisa Westerfield
Sent: Friday, June 13, 2008 7:07 AM
To: arslist@ARSLIST.ORG
Subject: Re: Can't move the Change ticket's Status beyond Request For
Authorization.

Sorry to jump in so late, but I would probably check the Approval
Process Mappings and see what status you have set to move to if there
are no approvers.  This is where you can set the status defaults for
each stage.

Also, if there is a 'Business Approval' stage/phase, and there are no
approvers defined, the change remains in Request for Change status and
requires the Change Manager or Change Assignee to move the change
forward.  (Sounds like you may have already tried this one.)

Also, if you want to run an arlog I would be happy to look at it to see
why the status isn't changing.

Thanks,
LisaD

-Original Message-
From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of lann
Sent: Friday, June 13, 2008 7:42 AM
To: arslist@ARSLIST.ORG
Subject: Re: Can't move the Change ticket's Status beyond Request For
Authorization.

There are no approvers displayed in the approal tab at all.

lann

Decou, Candace M wrote:
 
 Oh and also they should have the role for Infrastructure Change
Approver
 as well I think.
 :)
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 10:10 PM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 For the Assignee and Manager the Status field is Disabled.Iam trying
 to go
 to the next Status Request For Change .
 There are no pending approvals required ,so I feel the
assignee/manager
 can
 do the Status change,I clicked Approve in the Process Flow
accelerator
 and
 did a Save.But no Status change happened.
 
 Lann
 
 
 Decou, Candace M wrote:
 
 I think the Change Manager assignee needs to move the Change Request
 forward.  So, in other words, if I read this right, the Change
 Assignee
 is trying to move it forward but it requires some action on the part
 of
 one of the CAB members (Change Manager assignee).  Who is that person
 or
 group?  Try having them select 'Approve' then move on to the next

Re: Can't move the Change ticket's Status beyond Request For Authorization.

2008-06-12 Thread Decou, Candace M
But when 'you' did this, were you logged in as someone in the group for
Change Assignee, or as someone in the group for Change Manager?  Also,
are you or is this person who is attempting this set up with appropriate
roles for the group to include Infrastructure Change Manager?  It could
be that you don't have the proper 'roles' or groups set for yourself?
This is just a guess.  The people who you set up as Change Managers must
be in the Change Management group (whatever you are calling it) and they
must also have the Infrastructure Change Manager role assigned and they
must also be set to Available.
Keep us posted - I am making certain assumptions here on the setup in
your environment, so not sure if I am hitting the mark for you or not.
:) 

Candace DeCou

DOI Remedy Systems Analyst 
Verizon Business 
Office:  (408) 371-1112

Email: [EMAIL PROTECTED] 

 

Verizon Business - global capability, personal accountability. 

This e-mail is strictly confidential and intended only for use by the
addressee unless otherwise indicated


-Original Message-
From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of lann
Sent: Wednesday, June 11, 2008 10:10 PM
To: arslist@ARSLIST.ORG
Subject: Re: Can't move the Change ticket's Status beyond Request For
Authorization.

For the Assignee and Manager the Status field is Disabled.Iam trying
to go
to the next Status Request For Change .
There are no pending approvals required ,so I feel the assignee/manager
can
do the Status change,I clicked Approve in the Process Flow accelerator
and
did a Save.But no Status change happened.

Lann


Decou, Candace M wrote:
 
 I think the Change Manager assignee needs to move the Change Request
 forward.  So, in other words, if I read this right, the Change
Assignee
 is trying to move it forward but it requires some action on the part
of
 one of the CAB members (Change Manager assignee).  Who is that person
or
 group?  Try having them select 'Approve' then move on to the next
stage
 and see if that helps.
 :)
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of J.T. Shyman
 Sent: Wednesday, June 11, 2008 4:54 AM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 What do you mean by unable to move...? Is there an error message or
is
 the
 status field disabled?
 
 --- J.T. Shyman
 
  -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 7:46 AM
 To: arslist@ARSLIST.ORG
 Subject: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 Iamstuck with a problem
 
 The assignee and manager of a Change Request are unable to move the
 Change
 ticket's Status beyond Request For Authorization. 
 I ensure the following:
 Assigne ehas  Infrastructure Change Assignee role-Fixed
Permission. 
 Availability is Yes 
 No approvers in Review Phase. 
 Added the assignee as Adhoc approver and tried ,but in vain
  
 Any other configuration I missed out?
 Any ideas will be greatly appreciated.
 Thx
 Lann
 
 -- 
 View this message in context:

http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-R
 eque
 st-For-Authorization.-tp17775621p17775621.html
 Sent from the ARS (Action Request System) mailing list archive at
 Nabble.com.
 


 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 


 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 


___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 

-- 
View this message in context:
http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-R
equest-For-Authorization.-tp17775621p17792536.html
Sent from the ARS (Action Request System) mailing list archive at
Nabble.com.


___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org

Re: Can't move the Change ticket's Status beyond Request For Authorization.

2008-06-12 Thread Decou, Candace M
Oh and also they should have the role for Infrastructure Change Approver
as well I think.
:)

Candace DeCou

DOI Remedy Systems Analyst 
Verizon Business 
Office:  (408) 371-1112

Email: [EMAIL PROTECTED] 

 

Verizon Business - global capability, personal accountability. 

This e-mail is strictly confidential and intended only for use by the
addressee unless otherwise indicated


-Original Message-
From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of lann
Sent: Wednesday, June 11, 2008 10:10 PM
To: arslist@ARSLIST.ORG
Subject: Re: Can't move the Change ticket's Status beyond Request For
Authorization.

For the Assignee and Manager the Status field is Disabled.Iam trying
to go
to the next Status Request For Change .
There are no pending approvals required ,so I feel the assignee/manager
can
do the Status change,I clicked Approve in the Process Flow accelerator
and
did a Save.But no Status change happened.

Lann


Decou, Candace M wrote:
 
 I think the Change Manager assignee needs to move the Change Request
 forward.  So, in other words, if I read this right, the Change
Assignee
 is trying to move it forward but it requires some action on the part
of
 one of the CAB members (Change Manager assignee).  Who is that person
or
 group?  Try having them select 'Approve' then move on to the next
stage
 and see if that helps.
 :)
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of J.T. Shyman
 Sent: Wednesday, June 11, 2008 4:54 AM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 What do you mean by unable to move...? Is there an error message or
is
 the
 status field disabled?
 
 --- J.T. Shyman
 
  -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 7:46 AM
 To: arslist@ARSLIST.ORG
 Subject: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 Iamstuck with a problem
 
 The assignee and manager of a Change Request are unable to move the
 Change
 ticket's Status beyond Request For Authorization. 
 I ensure the following:
 Assigne ehas  Infrastructure Change Assignee role-Fixed
Permission. 
 Availability is Yes 
 No approvers in Review Phase. 
 Added the assignee as Adhoc approver and tried ,but in vain
  
 Any other configuration I missed out?
 Any ideas will be greatly appreciated.
 Thx
 Lann
 
 -- 
 View this message in context:

http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-R
 eque
 st-For-Authorization.-tp17775621p17775621.html
 Sent from the ARS (Action Request System) mailing list archive at
 Nabble.com.
 


 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 


 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 


___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 

-- 
View this message in context:
http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-R
equest-For-Authorization.-tp17775621p17792536.html
Sent from the ARS (Action Request System) mailing list archive at
Nabble.com.


___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are


Can't move the Change ticket's Status beyond Request For Authorization.

2008-06-11 Thread lann
Iamstuck with a problem

The assignee and manager of a Change Request are unable to move the Change
ticket's Status beyond Request For Authorization. 
I ensure the following:
Assigne ehas  Infrastructure Change Assignee role-Fixed Permission. 
Availability is Yes 
No approvers in Review Phase. 
Added the assignee as Adhoc approver and tried ,but in vain
 
Any other configuration I missed out?
Any ideas will be greatly appreciated.
Thx
Lann

-- 
View this message in context: 
http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-Request-For-Authorization.-tp17775621p17775621.html
Sent from the ARS (Action Request System) mailing list archive at Nabble.com.

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are


Re: Can't move the Change ticket's Status beyond Request For Authorization.

2008-06-11 Thread J.T. Shyman
What do you mean by unable to move...? Is there an error message or is the
status field disabled?

--- J.T. Shyman

 -Original Message-
From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of lann
Sent: Wednesday, June 11, 2008 7:46 AM
To: arslist@ARSLIST.ORG
Subject: Can't move the Change ticket's Status beyond Request For
Authorization.

Iamstuck with a problem

The assignee and manager of a Change Request are unable to move the Change
ticket's Status beyond Request For Authorization. 
I ensure the following:
Assigne ehas  Infrastructure Change Assignee role-Fixed Permission. 
Availability is Yes 
No approvers in Review Phase. 
Added the assignee as Adhoc approver and tried ,but in vain
 
Any other configuration I missed out?
Any ideas will be greatly appreciated.
Thx
Lann

-- 
View this message in context:
http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-Reque
st-For-Authorization.-tp17775621p17775621.html
Sent from the ARS (Action Request System) mailing list archive at
Nabble.com.


___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are


Re: Can't move the Change ticket's Status beyond Request For Authorization.

2008-06-11 Thread Decou, Candace M
I think the Change Manager assignee needs to move the Change Request
forward.  So, in other words, if I read this right, the Change Assignee
is trying to move it forward but it requires some action on the part of
one of the CAB members (Change Manager assignee).  Who is that person or
group?  Try having them select 'Approve' then move on to the next stage
and see if that helps.
:)

Candace DeCou

DOI Remedy Systems Analyst 
Verizon Business 
Office:  (408) 371-1112

Email: [EMAIL PROTECTED] 

 

Verizon Business - global capability, personal accountability. 

This e-mail is strictly confidential and intended only for use by the
addressee unless otherwise indicated


-Original Message-
From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of J.T. Shyman
Sent: Wednesday, June 11, 2008 4:54 AM
To: arslist@ARSLIST.ORG
Subject: Re: Can't move the Change ticket's Status beyond Request For
Authorization.

What do you mean by unable to move...? Is there an error message or is
the
status field disabled?

--- J.T. Shyman

 -Original Message-
From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of lann
Sent: Wednesday, June 11, 2008 7:46 AM
To: arslist@ARSLIST.ORG
Subject: Can't move the Change ticket's Status beyond Request For
Authorization.

Iamstuck with a problem

The assignee and manager of a Change Request are unable to move the
Change
ticket's Status beyond Request For Authorization. 
I ensure the following:
Assigne ehas  Infrastructure Change Assignee role-Fixed Permission. 
Availability is Yes 
No approvers in Review Phase. 
Added the assignee as Adhoc approver and tried ,but in vain
 
Any other configuration I missed out?
Any ideas will be greatly appreciated.
Thx
Lann

-- 
View this message in context:
http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-R
eque
st-For-Authorization.-tp17775621p17775621.html
Sent from the ARS (Action Request System) mailing list archive at
Nabble.com.



___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are


___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are


Re: Can't move the Change ticket's Status beyond Request For Authorization.

2008-06-11 Thread lann
For the Assignee the Status field is Disabled.Iam trying to go to the next
Status Request For Change .
There are no pending approvals required ,so I feel the assignee can do the
Status change,I clicked Approve in the Process Flow accelerator and did a
Save.But no Status change happened.

Lann


J.T. Shyman wrote:
 
 What do you mean by unable to move...? Is there an error message or is
 the
 status field disabled?
 
 --- J.T. Shyman
 
  -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 7:46 AM
 To: arslist@ARSLIST.ORG
 Subject: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 Iamstuck with a problem
 
 The assignee and manager of a Change Request are unable to move the Change
 ticket's Status beyond Request For Authorization. 
 I ensure the following:
 Assigne ehas  Infrastructure Change Assignee role-Fixed Permission. 
 Availability is Yes 
 No approvers in Review Phase. 
 Added the assignee as Adhoc approver and tried ,but in vain
  
 Any other configuration I missed out?
 Any ideas will be greatly appreciated.
 Thx
 Lann
 
 -- 
 View this message in context:
 http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-Reque
 st-For-Authorization.-tp17775621p17775621.html
 Sent from the ARS (Action Request System) mailing list archive at
 Nabble.com.
 
 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 

-- 
View this message in context: 
http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-Request-For-Authorization.-tp17775621p17792517.html
Sent from the ARS (Action Request System) mailing list archive at Nabble.com.

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are


Re: Can't move the Change ticket's Status beyond Request For Authorization.

2008-06-11 Thread lann
For the Assignee and Manager the Status field is Disabled.Iam trying to go
to the next Status Request For Change .
There are no pending approvals required ,so I feel the assignee/manager can
do the Status change,I clicked Approve in the Process Flow accelerator and
did a Save.But no Status change happened.

Lann


Decou, Candace M wrote:
 
 I think the Change Manager assignee needs to move the Change Request
 forward.  So, in other words, if I read this right, the Change Assignee
 is trying to move it forward but it requires some action on the part of
 one of the CAB members (Change Manager assignee).  Who is that person or
 group?  Try having them select 'Approve' then move on to the next stage
 and see if that helps.
 :)
 
 Candace DeCou
 
 DOI Remedy Systems Analyst 
 Verizon Business 
 Office:  (408) 371-1112
 
 Email: [EMAIL PROTECTED] 
 
  
 
 Verizon Business - global capability, personal accountability. 
 
 This e-mail is strictly confidential and intended only for use by the
 addressee unless otherwise indicated
 
 
 -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of J.T. Shyman
 Sent: Wednesday, June 11, 2008 4:54 AM
 To: arslist@ARSLIST.ORG
 Subject: Re: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 What do you mean by unable to move...? Is there an error message or is
 the
 status field disabled?
 
 --- J.T. Shyman
 
  -Original Message-
 From: Action Request System discussion list(ARSList)
 [mailto:[EMAIL PROTECTED] On Behalf Of lann
 Sent: Wednesday, June 11, 2008 7:46 AM
 To: arslist@ARSLIST.ORG
 Subject: Can't move the Change ticket's Status beyond Request For
 Authorization.
 
 Iamstuck with a problem
 
 The assignee and manager of a Change Request are unable to move the
 Change
 ticket's Status beyond Request For Authorization. 
 I ensure the following:
 Assigne ehas  Infrastructure Change Assignee role-Fixed Permission. 
 Availability is Yes 
 No approvers in Review Phase. 
 Added the assignee as Adhoc approver and tried ,but in vain
  
 Any other configuration I missed out?
 Any ideas will be greatly appreciated.
 Thx
 Lann
 
 -- 
 View this message in context:
 http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-R
 eque
 st-For-Authorization.-tp17775621p17775621.html
 Sent from the ARS (Action Request System) mailing list archive at
 Nabble.com.
 
 
 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 ___
 UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
 Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are
 
 

-- 
View this message in context: 
http://www.nabble.com/Can%27t-move-the-Change-ticket%27s-Status-beyond-Request-For-Authorization.-tp17775621p17792536.html
Sent from the ARS (Action Request System) mailing list archive at Nabble.com.

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: Where the Answers Are