I have a project intended to be fully sprinkled with a combustible attic that tapers from 2' to 4 ' without being filled to within 2 inches of the deck with insulation. So I am planning on a dry pipe system with standard heads as the design of the attic does not allow the effective use of special application attic sprinklers.
The questions are: whether inspection access is required to be provided, is it prudent to do so at the heads, or can the locations just be noted on the gypsum mounted to the bottom chord of the open web trusses. TIA David T Williams, PE - Lead MEP/FP Engineer 21 West Superior Street, Suite 500, Duluth, MN 55802 Direct 218.279.2436 | Cell 218.310.2446 LHBcorp.com<http://www.LHBcorp.com> LHB, Inc. | PERFORMANCE DRIVEN DESIGN.