+1 to delaying 2 weeks. I think it will be prudent to wait in this case. There is too much in flux with Gradle migration currently and based on Scott's latest update I think we will be in a more stable state in 2 weeks. Last Beam release date was 3/20 and our plan was to make a release every 6 weeks. Even if we start cutting a release in 2 weeks (~4/26), we will have more than a week to finish that release. Even if that is not enough time to finish a release it will put is in the proximity of the 5/5 target date. I prefer that option, to another potential release with Maven.
On Wed, Apr 11, 2018 at 1:22 PM, Romain Manni-Bucau <rmannibu...@gmail.com> wrote: > Any hope the release is on central before the 30th? > I do not think this was the plan to begin with. The time between the previous release and 4/30 is less than 6 weeks. > > Le 11 avr. 2018 22:02, "Robert Bradshaw" <rober...@google.com> a écrit : > >> +1 to keeping up the regular release cycle, but I don't think it makes >> sense to cut until we're ready to actively work on the release. A cut date >> two weeks from now seems fine (unless someone else is volunteering to do it >> this time around). >> >> That being said, a dry run using gradle now may make a lot of sense, >> giving us a couple of weeks to iron out the kinks, if any. >> >> On Wed, Apr 11, 2018 at 12:58 PM Chamikara Jayalath <chamik...@google.com> >> wrote: >> >>> Hi JB, >>> >>> Please note that I opened a blocker [1] (working on it) and looks like >>> we have several other JIRAs marked for 2.5.0. So +1 for waiting for two >>> weeks (or till JIRAs are resolved or moved off the list). >>> >>> Thanks, >>> Cham >>> >>> [1] https://issues.apache.org/jira/browse/BEAM-3991 >>> [2] https://issues.apache.org/jira/issues/?jql=project%20%3D >>> %20BEAM%20AND%20resolution%20%3D%20Unresolved%20AND%20fixVer >>> sion%20%3D%202.5.0%20ORDER%20BY%20priority%20DESC >>> >>> On Wed, Apr 11, 2018 at 12:28 PM Jean-Baptiste Onofré <j...@nanthrax.net> >>> wrote: >>> >>>> Hi guys, >>>> >>>> Due to the last work, I think it makes sense to try a release using >>>> Gradle. If it doesn't work smoothly, we will rollback to Maven, and >>>> maybe in that case, we should ask ourselves if Gradle is really a good >>>> alternative for now. >>>> >>>> I'm in vacation tomorrow morning for 2 weeks. I can cut the release >>>> tomorrow end of the morning (my time). But in the case we need some >>>> additional PR merges or we have some work in progress, I'm proposing to >>>> postpone 2.5.0 release for the end of this month (in two weeks). If >>>> someone is volunteer to tackle this release, please, let us know. >>>> >>>> Regards >>>> JB >>>> >>>> On 06/04/2018 10:48, Jean-Baptiste Onofré wrote: >>>> > Hi guys, >>>> > >>>> > Apache Beam 2.4.0 has been released on March 20th. >>>> > >>>> > According to our cycle of release (roughly 6 weeks), we should think >>>> about 2.5.0. >>>> > >>>> > I'm volunteer to tackle this release. >>>> > >>>> > I'm proposing the following items: >>>> > >>>> > 1. We start the Jira triage now, up to Tuesday >>>> > 2. I would like to cut the release on Tuesday night (Europe time) >>>> > 2bis. I think it's wiser to still use Maven for this release. Do you >>>> think we >>>> > will be ready to try a release with Gradle ? >>>> > >>>> > After this release, I would like a discussion about: >>>> > 1. Gradle release (if we release 2.5.0 with Maven) >>>> > 2. Isolate release cycle per Beam part. I think it would be >>>> interesting to have >>>> > different release cycle: SDKs, DSLs, Runners, IOs. That's another >>>> discussion, I >>>> > will start a thread about that. >>>> > >>>> > Thoughts ? >>>> > >>>> > Regards >>>> > JB >>>> > >>>> >>>